2025-06-20County road 4540 Madlaveien-Regimentsveien Roundabout and measures for soft road users (Rogaland fylkeskommune)
Rogaland County needs to implement the project County Road 4540 Madlaveien-Regimentsveien. Roundabout and measures for soft road usersVisers to the detailed development plan for the area where a large-scale residential development has started in accordance with the area plan for Madla-Revheim. There is, therefore, a need to upgrade the relevant junction. The crossing is an order requirement in the area plan for Madla-Revheim.
Vis anskaffelsen »
2023-10-022023-103 City Package Ålesund - County road 60 Blindheim - Flisnes (Møre og Romsdal fylkeskommune)
1. About the assignment - purpose and scope of the procurement
Major housing development has been carried out along county road 60 between Blindheim and Flisnes in recent years, and there are plans to develop more residential areas. The county road is also an important thoroughfare, between the Magerholm-Sykkylven ferry connection.
More than 11,000 cars drive along the stretch per day, and the road system is not designed for current or future traffic. The aim of the project is to improve road safety for …
Vis anskaffelsen »
2023-06-15County road 3068 Foot and cycle path Dølebakken - Lingelemveien (Vestfold og Telemark Fylkeskommune)
County road 3068 Lingelemveien is to be improved and a two-sided pavement and cycle lane is to be constructed. In addition the current junction at Ringveien - Lingelemveien is to be altered to a roundabout.
Sandefjord Municipality will renew the water and sewage installations on the same stretch.
New street lights will be established in Lingelemveien and at the roundabout.
The work will be carried out as a joint project where Vestfold and Telemark County and Sandefjord Municipality are the contracting …
Vis anskaffelsen » Nevnte leverandører:Isachsen Anlegg AS
2022-06-23County road 547 centre of Åkra - Bt1a (Rogaland fylkeskommune)
Rogaland County needs to implement the following project: County 547 centre of Åkra - Bt1a. The project consists of the construction of a new roundabout in the centre of Åkra, and a new road between the centre of Åkra and Tostemvegen. The total road length including all side roads is approx. 1500 m. An existing junction in the centre of Åkra is to be altered to a roundabout. A new local road with a new roundabout is to be constructed between the roundabout in the centre and Tostemvegen at Årvollsåna.
Vis anskaffelsen » Nevnte leverandører:Bertelsen & Garpestad AS
2020-12-21Infrastructure Atlanteren BT1 (Stavanger kommune)
The contracting authority would like to use this contest to enter into a contract for work for building infrastructure in the development area Atlanteren, BT1 at Hundvåg in Stavanger Municipality. The work includes, amongst other things, water and sewage, roads, construction, landscape, laying of cables.
Vis anskaffelsen » Nevnte leverandører:Risa As
2020-03-06County Road 313 Klokkerjordet — Holmestrand Municipality (Vestfold og Telemark Fylkeskommune)
Project county road 313 Klokkerjordet involves alterations to the county road on a stretch of approx. 1 000 m (Hp02 km 500-km 1 500). Two new roundabouts and two new pedestrian and bicycle culverts are to be constructed. In addition, county road 3248 Hagaveien is to be altered and connected to a new roundabout in the north. The existing Bøplassen bridge is to be demolished.
Vis anskaffelsen »
2020-01-30Contract 7007 Roundabout Strandveien (Helse Sør-Øst RHF)
The contract consists of the development of a new roundabout with a diameter of 50 m on the current county road 282 Strandveien, as well as 2 short arms to the side. The roundabout will have the same look as the existing roundabout in Strandveien. The contract also includes moving the existing foot/cycle path on the sea side, as well as demolishing and establishing a new surface water system and lighting.
Vis anskaffelsen » Nevnte leverandører:Marthinsen and Duvholt AS
2019-06-03Access Road to Tangenvika Bridge (Bane NOR SF)
The performance contract is a preliminary contract for the double-track development Kleverud-Åkersvika.
The contract consists of 5 main parts:
1) Roundabout and permanent road;
2) Approach road to Furnesodden;
3) Foot and cycle path from Tangen school to Kongspartvegen;
4) Temporary site road;
5) Option for conveying water and sewage.
Vis anskaffelsen » Nevnte leverandører:John Galten AS
2014-11-12117-BYM-2014 Street terminal Stovner underground station and Linjeparken (Oslo kommune Bymiljøetaten)
The Town Environment Department shall procure contractors to construct a street terminal for Stovner underground station and Linjeparken, as well as alterations to the existing road network. The project consists of altering the existing road outside the Stovner centre, constructing a street terminal i Fossumveien, as well as developing Linjeparken, which is one of four district parks in Groruddalen.
Vis anskaffelsen » Nevnte leverandører:Steen & Lund AS
2011-08-29E6 Havnekrysset - Kvithammar (S-E-7) (Statens vegvesen Region midt)
This contract is part of the road project E6 Trondheim - Stjørdal. The contract covers the stretch from the newly established roundabout at Havnekrysset (approx. per. 2780) and north to the Kvithammar (about per. 5200). Approx. 2570 m 4-lane E6, with central reservation, will be built on said stretch.
A plan divided intersection with Fv. 38 shall be constructed at Kvithammar incl. ramps, two roundabouts and flyover of E6. Further, corresponding flyovers (L=approx 50m) shall be built over E6 for …
Vis anskaffelsen » Nevnte leverandører:Peab Sverige Ab Nuf
2011-08-22Gildheim - Grillstad (T-Ø-E-5) (Statens vegvesen Region midt)
The contract is a part of the project E6 Trondheim – Stjørdal, lot Trondheim, a project which consists of several contracts. Contract no. T-Ø-E-5 Gildheim – Grillstad goes along national road 706 in Trondheim municipality from Leangen/Gildheim in the west to Grillstad tunnel in the east.
On the stretch Gildheim-Grillstad, the current national road 706 is to be expanded from two to four lanes. This also involves the construction of several new constructions. In particular the junction area between …
Vis anskaffelsen » Nevnte leverandører:Reinertsen AS v/ Erik Reinertsen
2011-02-07Open air zone E14 and Ring Road North, lot A (Statens vegvesen Region midt)
This contract is included in the road project E6 Trondheim – Stjørdal and is the 6th sub contract to be started on the Stjørdals lot in this project. It is the last part of the stretch Værnes – Havnekrysset.
The contract consists of three construction objects with various geographical locations:
"Dagsone E14", "Driftsvegkulvert" for Avinor and "Ringveg Nord, parsell A".
The total amount included is approx. 400 m of 4 lane road, 950 m foot/cycle path. Futhermore there are 3 roundabouts, 2 railway bridges, …
Vis anskaffelsen » Nevnte leverandører:Grunnarbeid As