Nyeste anskaffelser av fjerning av øvre jordsmonn i Norge
2020-05-13New Fjelltun School, Contract 3 Groundwork (Strand kommune)
New Fjelltun School, construction stage 1. Contract 3 groundwork.
New Fjelltun School and construction stage 1 of the outside area is to be constructed in accordance with the preliminary project and within the cost limit of NOK 330 million.
The new school must be ready for the start of the school year in 2022.
The groundwork includes, amongst other things:
— excavation of the building pit,
— ditches for water and sewage and cables,
— bus stop,
— road and foot/cycle path,
— car park.
Vis anskaffelsen » Nevnte leverandører:Stangeland Maskin AS
2017-08-22County road 243 the Crossing of Sifjorden (Statens vegvesen Region nord)
The project includes construction works for a new road connection over Sifjorden. The masses shall be blasted and transported from a side gravel pit at the farther end of fjord and be deposited in the sea filling. The first layer of masses shall be deposited by using seagoing equipment to contour line — 20 metres. The remaining masses shall be deposited by using on shore excavators Masses shall be deposited from both sides of the fjord due to the construction of a 45 metres bridge in the middle of the …
Vis anskaffelsen »
2015-05-11Waste sorting plant, Sandnes — Groundworks 1 (IVAR IKS)
Vegetation clearing, excavation and transportation of 0.5 m topsoil + silt and sand layer to 1.7 under planned foundations on the construction area/site. Transport, back-filling//surface — blasted stone and compression of delivered matter to planned course level. Total affected area 17 000 m.
Vis anskaffelsen » Nevnte leverandører:Bjelland Entreprenør As
2015-03-26Contract B10 (Alstahaug havnevesen KF)
The contract is for blasting out and roughly levelling area K3 and the plot on area I3, establishing of fences, gates and ditches as well as a filling of blasted stone in the sea (in jetties) from approx. contour -4 m to approx. contour +3.4 m. Additional option for a filling in the sea with barges from the seabed and up to approx. contour -4 m (foot jetties).
Vis anskaffelsen »
2015-02-05Framework agreement, excavation, blasting and transport services (Ski Kommune)
With this Ski kommune, henceforth referred to as the contracting authority, requests tender for a framework agreement involving excavation, blasting and transport services. In connection with ongoing operations and maintenance of the contracting authority's buildings, outdoor areas, water and sewage systems, etc., there will be a requirement for excavation and landscape gardening works, with accompanying transport of machines, equipment and masses. The contracting authority has a requirement for …
Vis anskaffelsen » Nevnte leverandører:Alvim EntreprenørHerstad ASSvein Grøstad
2014-12-03The conveying of the main infrastructure to F-35 (Forsvarsbygg)
Project 5000408 main infrastructure work for F-35 comprises the excavation of a large ditch, partially deep and wide, as well as the delivery and laying of waste water pipelines, surface water pipelines, water pipelines, high-tension electricity cables, district heating and remote cooling pipes and ICT drawing pipes. Development of a street and pavement on parts of the ditch route.
The contract will mainly consist of:
— Foundation works.
— Roadworks.
— Delivery and laying of water pipelines.
— Delivery …
Vis anskaffelsen » Nevnte leverandører:THOR GJUL AS