Anskaffelser: Dampturbinegenerator og relaterte apparater
Én aktiv anskaffelse
Dampturbinegenerator og relaterte apparater har blitt anskaffet av organisasjoner som BIR AS, Eidsiva Bioenergi AS og Forsvarets logistikkorganisasjon (FLO).
Historisk har leverandører innenfor dette området vært AS Fadum Tekniske og Rainpower Small Hydro AS.
- Elektrisk maskineri, apparater, utstyr og forbruksvarer; Belysning (18 nye anskaffelser)
- Elektriske motorer, generatorer og transformatorer (8)
- Generatorer (3)
- Dampturbinegenerator og relaterte apparater (1) ⬅️
Nyeste anskaffelser av dampturbinegenerator og relaterte apparater i Norge
2026-09-08
Deadline 2026-10-28
Long-term preventive service agreement for the two steam turbines at BIR Waste incineration plant in Rådal (BIR AS)
The extent of the work included in this agreement is the provision of long-term preventive maintenance services, technical support and follow-up services for the two steam turbine generator units and the accompanying auxiliary systems at BIR ́s waste incineration facility in Bergen, Norway. The scope shall cover all necessary services and all assistance required for the planning and execution of preventive and corrective maintenance of the two steam turbine generator units, including, but not limited to: … Vis anskaffelsen »
The extent of the work included in this agreement is the provision of long-term preventive maintenance services, technical support and follow-up services for the two steam turbine generator units and the accompanying auxiliary systems at BIR ́s waste incineration facility in Bergen, Norway. The scope shall cover all necessary services and all assistance required for the planning and execution of preventive and corrective maintenance of the two steam turbine generator units, including, but not limited to: … Vis anskaffelsen »
2014-06-22
Framework agreement, electricity supply (generator) and electric pylon generator (Forsvarets logistikkorganisasjon (FLO))
Diesel and electricity supply. Electric pylon. Vis anskaffelsen »
Diesel and electricity supply. Electric pylon. Vis anskaffelsen »
2011-09-06
Skarg power plant: electro/mechanical package (Otra Kraft DA)
One singel contract covering: Vis anskaffelsen »
One singel contract covering: Vis anskaffelsen »
2011-08-12
041-2011: process equipment for combined heat & power plant (CHP) using waste wood (Eidsiva Bioenergi AS)
Process equipment for combined heat & power plant (CHP) to produce power, process steam and district heating. This means for example boiler, furnace (bio and gas) equipment for flue gas treatment, ash handling, necessary purification equipment, electrical installation, piping system and necessary completions inside the energy central. Bio-power plant approx. 25 MW. The plant will deliver approximately 200 GWh energy. The fuel is based on recycled wood and logging waste. (This procurement does not include … Vis anskaffelsen »
Process equipment for combined heat & power plant (CHP) to produce power, process steam and district heating. This means for example boiler, furnace (bio and gas) equipment for flue gas treatment, ash handling, necessary purification equipment, electrical installation, piping system and necessary completions inside the energy central. Bio-power plant approx. 25 MW. The plant will deliver approximately 200 GWh energy. The fuel is based on recycled wood and logging waste. (This procurement does not include … Vis anskaffelsen »
2011-04-18
Electromechanical equipment for Nye Folkedal Kraftverk (New Folkedal Power Plant) (Norconsult AS (Forsyning))
Hardanger Energi AS is planning to construct a new power plant which shall replace the old power plant. The new power plant will have a complete new waterway. The following main components and construction parts are including in the delivery (subject-matter of the contract): — 2 Pelton turbines, — 2 synchronous generators, — apparatus and control system, — 2 main stop valves, — inlet pipes, — cooling water system, — electrotechnical equipment for dam at Svortetjørn. NOTE: To register your interest in … Vis anskaffelsen »
Hardanger Energi AS is planning to construct a new power plant which shall replace the old power plant. The new power plant will have a complete new waterway. The following main components and construction parts are including in the delivery (subject-matter of the contract): — 2 Pelton turbines, — 2 synchronous generators, — apparatus and control system, — 2 main stop valves, — inlet pipes, — cooling water system, — electrotechnical equipment for dam at Svortetjørn. NOTE: To register your interest in … Vis anskaffelsen »