2011-04-18Electromechanical equipment for Nye Folkedal Kraftverk (New Folkedal Power Plant) (Norconsult AS (Forsyning))
Hardanger Energi AS is planning to construct a new power plant which shall replace the old power plant. The new power plant will have a complete new waterway.
The following main components and construction parts are including in the delivery (subject-matter of the contract):
— 2 Pelton turbines,
— 2 synchronous generators,
— apparatus and control system,
— 2 main stop valves,
— inlet pipes,
— cooling water system,
— electrotechnical equipment for dam at Svortetjørn.
NOTE: To register your interest in …
Vis anskaffelsen » Nevnte leverandører:AS Fadum Tekniske
2011-04-18Feed pipe for Nye Folkedal Kraftverk (new Folkedal power plant) (Norconsult AS (Forsyning))
2 steel pipes through concrete plug in tunnel;
1 access pipe with gate through concrete plug;
1 pipe rupture valve;
2 air valves;
1 feed pip
Note: to register your interest in this notice and obtain any additional information please visit the Doffin web site at http://www.doffin.no/Search/Search_Switch.aspx?ID=228958.
Vis anskaffelsen »