Antall eller omfang
Electromechanical equipment for Nye Folkedal Kraftverk (New Folkedal Power Plant). The main components comprise:— 2 Pelton turbines,— 2 synchronous generators,— apparatus and control system,— 2 main stop valves,— inlet pipes,— cooling water system,— electrotechnical equipment for dam at Svortetjørn.The contract also includes project management and administration, engineering design, procurement, plant and testing of plant, preparatory works at the installation site, transport, installation, clearing and waste management, training, testing and commissioning, documentation and spare parts.9 500 00014 000 000