2024-06-21   Procurement of 132/22/11 kV three winding transformers (BKK AS)
This is an invitation to tender for delivery of 2 pcs.132/22/11 kV three winding transformers 40/25/25 / 50/31.5/31.5 VAT ONAN/ONAF. Both transformers are to be delivered to Breivik transformer station in Bergen municipality in Vestland county. Preferred delivery time is Q2/Q3 2026, latest delivery is 31.08.2024.Information on the Deliverables can be found in Appendix A – Work description and corresponding appendices listed below. Vis anskaffelsen »
2021-06-29   Procurement of Emergency Preparedness Transformers for the Norwegian Electricity Grid (REN Transformatorberedskap AS)
On behalf of the members of the Norwegian emergency preparedness scheme, 4 emergency preparedness transformers with associated equipment shall be acquired for the Norwegian electricity grid for long-term storage in Norway. Vis anskaffelsen »
2021-02-09   Request for Delivery of Transformers 2021-2023 (Voss Energi Nett AS)
Energiforum Vest (EV) would like tenders for a framework agreement for the delivery of transformers. The contract period will be 2 years, (2021-2023), with an option for 1 + 1 year. Vis anskaffelsen »
2016-10-14   Framework agreement; prefabricated net stations, boards, switches and transformers (Helgeland Kraft AS)
Helgeland Kraft AS and Nordlandsnett AS wish to enter into a long-term framework agreement with a joint supplier for the purchase of the following product groups: The companies wish to enter into a long-term framework agreement with a joint supplier for the purchase of the following product groups: — -Prefabricated net stations (with or without boards and switchgears and transformers) — -Accompanying boards and switches — -Transformers for distribution networks. — Option 1: A stand-by arrangement for the … Vis anskaffelsen »
2013-05-06   Purchase of a new transformer. RT1 at the Mosjøen transforming station (Helgelandskraft AS)
Helgeland Kraft is the operator of the activities within the production, transmission and distribution of renewable energy as well as other activities of natural conjunction. Our 273 employees work towards our vision: Helgelandskraft - an active value creator for the region. We are certified acc. to ISO 9001/14001 and have a strong focus on preventive health, environment and safety work. On a national scale, Helgelandskraft is a large power company with over 42,000 customers and with a power production … Vis anskaffelsen »
2011-01-24   Request for tenders – Framework agreement 2011-2013 with option for 1 year prolongation (Nettalliansen AS)
Framework agreement. Purchase of: Cable line and cable conduits. Network stations, transformers and switch system. Electric plant materials. NOTE: To register your interest in this notice and obtain any additional information please visit the Doffin Web Site at http://www.doffin.no/Search/Search_Switch.aspx?ID=221999. Vis anskaffelsen »