Procurement of Electromechanical Delivery Consisting of Water Turbine, Generator, Regulator and Control System for Hydro-electric Power Station in Sikkilsdalen
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken (Skål Creek). This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption. The goals of the project are to have a power station solution that gives: • stable power supply based on the owner's need for power; • low annual operating costs/maintenance costs; • equipment/components of high quality that have long shelf-life. To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
Frist
Fristen for mottak av tilbud var 2021-09-01.
Anskaffelsen ble publisert 2021-07-02.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2021-07-02) Gjenstand Anskaffelsens omfang
Tittel: Turbines and motors
Referansenummer: 17/71-1
Kort beskrivelse:
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken (Skål Creek). This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m
The goals of the project are to have a power station solution that gives:
• stable power supply based on the owner's need for power;
• low annual operating costs/maintenance costs;
• equipment/components of high quality that have long shelf-life.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken (Skål Creek). This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m
The goals of the project are to have a power station solution that gives:
• stable power supply based on the owner's need for power;
• low annual operating costs/maintenance costs;
• equipment/components of high quality that have long shelf-life.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Varer
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Turbiner og motorer📦
Tilleggs-CPV: Bygge- og anleggsarbeid i forbindelse med Vannkraftanlegg📦 Utførelsessted
NUTS-region: Oslo
🏙️
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken (Skål Creek). This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m
The goals of the project are to have a power station solution that gives:
• stable power supply based on the owner's need for power;
• low annual operating costs/maintenance costs;
• equipment/components of high quality that have long shelf-life.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
Estimert totalverdi: 1 750 000 NOK 💰
Kort beskrivelse:
Sikkilsdalseter is located approx. 1 000 metres above sea-level in Sikkilsdalen in Nord-Fron Municipality. Electric power from a separate hydro-electric power station provides electricity to mountain farms. This power station supplies electricity only to Sikkilsdalseter, and runs in so called ‘island operation’. There is not an external power grid in to Sikkilsdalseter. The mountain farm consists of approx. 14 buildings of varying size that receive electricity from the hydro-electric power station. A rough estimate of consumption is approx. 150 000 kilowatt hours (there is no exact measurement of actual consumption). A diesel aggregate is in reserve if the power station stops, where there is a separate switch-breaker. The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m
Sikkilsdalseter is located approx. 1 000 metres above sea-level in Sikkilsdalen in Nord-Fron Municipality. Electric power from a separate hydro-electric power station provides electricity to mountain farms. This power station supplies electricity only to Sikkilsdalseter, and runs in so called ‘island operation’. There is not an external power grid in to Sikkilsdalseter. The mountain farm consists of approx. 14 buildings of varying size that receive electricity from the hydro-electric power station. A rough estimate of consumption is approx. 150 000 kilowatt hours (there is no exact measurement of actual consumption). A diesel aggregate is in reserve if the power station stops, where there is a separate switch-breaker. The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m
Estimert verdi eksklusive mva: 1 750 000 NOK 💰
Varighet: 12 måneder
Juridisk, økonomisk, finansiell og teknisk informasjon Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten:
Requirements: tenderers must be a legally established company.
Documentation:
Norwegian companies: company registration certificate.
Foreign companies: proof that the company is registered in a trade or business register as prescribed by the law of the country where the company is established.
Økonomisk og finansiell stilling:
Requirement: paid taxes and duties.
Documentation:
A certificate, not older than 6 months, which verifies that the tenderer has fulfilled the obligations of payment of taxes, social security contributions and VAT. The certificate can be ordered and obtained from Altinn by using a separate link on skatteetaten.no.
A certificate, not older than 6 months, which verifies that the tenderer has fulfilled the obligations of payment of taxes, social security contributions and VAT. The certificate can be ordered and obtained from Altinn by using a separate link on skatteetaten.no.
Foreign tenderers must provide certificates from equivalent authorities to the Norwegian authorities.
Requirement: tenderers must be able to show adequate economic and financial capacity for the delivery.
A credit rating with key figures from a recognised credit assessment company, or other form of documentation to verify that the requirement has been met.
Teknisk og faglig kapasitet:
Requirement: the tenderer must have capacity to supply electromechanical delivery during August/September 2022.
Documentation:
A description of the tenderer's time capacity to implement the project in 2022. Tenderers are responsible for ensuring that the description is of such a nature that it documents fulfilment of the requirement.
Requirement:
The tenderer must have sufficient competence and experience in order to be able to implement the delivery (see technical description in Annex 1), where the tenderer must have the following qualification requirements:
Minimum 5 years experience with construction and delivery of Pelton turbines with associated generator, regulator and control system.
Delivery of at least five Pelton aggregates with turbine effect under 100 kW, with associated generator, regulator and control system.
Assignment list of the most relevant assignments with delivery of Pelton turbines and associated generator, regulator and control system.
Prosedyre
Rettslig grunnlag: 32014L0024
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Dato for åpning av tilbud: 2021-09-01 📅
Tidspunkt for åpning av tilbud: 12:00
Tildelingskriterier
Kvalitetskriterium (navn): Competence and experience of offered personnel
Kvalitetskriterium (vekting): 20
Kvalitetskriterium (navn): Assignment comprehension
Pris (vekting): 60
Utfyllende informasjon Klageinstans
Navn: Oslo Tingrett
Postadresse: Postboks 2106 Vika
Poststed: Oslo
Postnummer: 0125
Land: Norge 🇳🇴
Telefon: +47 22035200📞
E-post: oslo.tingrett@domstol.no📧
Internettadresse: http://www.domstol.no/otir🌏
Kilde: OJS 2021/S 129-344106 (2021-07-02)
Kunngjøring om tildeling av kontrakt (2022-03-07) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
The goals of the project are to have a power station solution that gives:
stable power supply based on the owner's need for power
low annual operating costs/maintenance costs
equipment/components of high quality that have long shelf-life.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
The goals of the project are to have a power station solution that gives:
stable power supply based on the owner's need for power
low annual operating costs/maintenance costs
equipment/components of high quality that have long shelf-life.
To realise the project equipment must be procured for the facility, specified in three tender requests. This contest concerns electromechanical delivery consisting of water turbine, generator, regulator and control system. See the separate contest for system configuration and operation and separate contest for battery for load balancing/stabilisation of grid.
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
Prosedyre
Tilbudstype: Ikke aktuelt
Referanse Datoer
Sendt dato: 2022-03-07 📅
Publiseringsdato: 2022-03-11 📅
Identifikatorer
Kunngjøringsnummer: 2022/S 050-131459
Refererer til kunngjøring: 2021/S 129-344106
OJ-S-utgave: 50
Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
stable power supply based on the owner's need for power
low annual operating costs/maintenance costs
equipment/components of high quality that have long shelf-life.
Sikkilsdalseter is located approx. 1,000 metres above sea-level in Sikkilsdalen in Nord-Fron Municipality. Electric power from a separate hydro-electric power station provides electricity to mountain farms. This power station supplies electricity only to Sikkilsdalseter, and runs in so called ‘island operation’. There is not an external power grid in to Sikkilsdalseter. The mountain farm consists of approx. 14 buildings of varying size that receive electricity from the hydro-electric power station. A rough estimate of consumption is approx. 150,000 kilowatt hours (there is no exact measurement of actual consumption). A diesel aggregate is in reserve if the power station stops, where there is a separate switch-breaker. The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
Sikkilsdalseter is located approx. 1,000 metres above sea-level in Sikkilsdalen in Nord-Fron Municipality. Electric power from a separate hydro-electric power station provides electricity to mountain farms. This power station supplies electricity only to Sikkilsdalseter, and runs in so called ‘island operation’. There is not an external power grid in to Sikkilsdalseter. The mountain farm consists of approx. 14 buildings of varying size that receive electricity from the hydro-electric power station. A rough estimate of consumption is approx. 150,000 kilowatt hours (there is no exact measurement of actual consumption). A diesel aggregate is in reserve if the power station stops, where there is a separate switch-breaker. The power station is located near mountain farms and utilises a drop of approx. 58 metres in Nørdre Skålbekken [Skål Creek]. This creek/river runs from Skåltjønna and further to Sikkilsdalsåa. The intake basin is approx. 200 m3, and the power station can therefore be considered a so-called run-of-river power station. A separate system has been established for control and regulation of consumption.
Prosedyre Tildelingskriterier
Kvalitetskriterium (navn): Competence and experience of offered personnel.
Tildeling av kontrakt
Dato for kontraktinngåelse: 2021-10-22 📅
Navn: Energi teknikk AS
Poststed: Seimsfoss
Postnummer: 5472
Land: Norge 🇳🇴 Vestlandet
🏙️ Informasjon om tilbud
Antall mottatte tilbud: 3
Kilde: OJS 2022/S 050-131459 (2022-03-07)