Oslo kommune, The Water and Sewage Authority (VAV) is responsible for the management of waterway facilities connected to the water supply. With so many watercourse facilities, there is continually a need for rehabilitation, re-evaluation, main inspection, flood calculations, dam breach wave calculations and assessments regarding classification. VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects. According to the regulation on dams, re-evaluations, flood calculation, dam breach wave calculations and technical plans must be performed by persons with authorised qualifications in the relevant specialist fields. Re-evaluations are part of VAV's inspection program. Other relevant measures and projects are the result of investigations and reviews carried out in-line with the agency's inspection program. VAV wants to enter into two four year parallel framework agreements with two consulting companies for advisory services, with an option to extend for 2 years + 2 years.
Frist
Fristen for mottak av tilbud var 2021-01-22.
Anskaffelsen ble publisert 2020-12-23.
Kunngjøring av konkurranse (2020-12-23) Gjenstand Anskaffelsens omfang
Tittel: Engineering design services
Referansenummer: Anskaffelse 63/2020
Kort beskrivelse:
Oslo kommune, The Water and Sewage Authority (VAV) is responsible for the management of waterway facilities connected to the water supply.
With so many watercourse facilities, there is continually a need for rehabilitation, re-evaluation, main inspection, flood calculations, dam breach wave calculations and assessments regarding classification.
VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects.
According to the regulation on dams, re-evaluations, flood calculation, dam breach wave calculations and technical plans must be performed by persons with authorised qualifications in the relevant specialist fields. Re-evaluations are part of VAV's inspection program.
Other relevant measures and projects are the result of investigations and reviews carried out in-line with the agency's inspection program.
VAV wants to enter into two four year parallel framework agreements with two consulting companies for advisory services, with an option to extend for 2 years + 2 years.
Oslo kommune, The Water and Sewage Authority (VAV) is responsible for the management of waterway facilities connected to the water supply.
With so many watercourse facilities, there is continually a need for rehabilitation, re-evaluation, main inspection, flood calculations, dam breach wave calculations and assessments regarding classification.
VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects.
According to the regulation on dams, re-evaluations, flood calculation, dam breach wave calculations and technical plans must be performed by persons with authorised qualifications in the relevant specialist fields. Re-evaluations are part of VAV's inspection program.
Other relevant measures and projects are the result of investigations and reviews carried out in-line with the agency's inspection program.
VAV wants to enter into two four year parallel framework agreements with two consulting companies for advisory services, with an option to extend for 2 years + 2 years.
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Tjenester
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Prosjektering📦
Tilleggs-CPV: Ingeniørtjenester📦 Utførelsessted
NUTS-region: Oslo og Akershus
🏙️
Prosedyre
Prosedyretype: Konkurranse med forhandling
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Oslo kommune, The Water and Sewage Authority (VAV) is responsible for the management of waterway facilities connected to the water supply.
With so many watercourse facilities, there is continually a need for rehabilitation, re-evaluation, main inspection, flood calculations, dam breach wave calculations and assessments regarding classification.
VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects.
According to the regulation on dams, re-evaluations, flood calculation, dam breach wave calculations and technical plans must be performed by persons with authorised qualifications in the relevant specialist fields. Re-evaluations are part of VAV's inspection program.
According to the regulation on dams, re-evaluations, flood calculation, dam breach wave calculations and technical plans must be performed by persons with authorised qualifications in the relevant specialist fields. Re-evaluations are part of VAV's inspection program.
Other relevant measures and projects are the result of investigations and reviews carried out in-line with the agency's inspection program.
VAV wants to enter into two four year parallel framework agreements with two consulting companies for advisory services, with an option to extend for 2 years + 2 years.
VAV is responsible for:
— 32 dams in the water supply;
— 12 dams that have been in the water supply or have a cleansing effect in the watercourse;
— 17 abutment dams/barrier dams;
— 7 transfer tunnels;
— 3 bypass tunnels;
— 9 decommissioned/partially decommissioned dams.
With so many watercourse facilities, there is continually a need for rehabilitation, re-evaluation, major inspections, flood calculations, dam breach wave calculations and assessments regarding classification.
Many dams do not satisfy requirements in the new Regulation for Safety of Watercourse Facilities that came into force 1 January 2010. VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects.
Many dams do not satisfy requirements in the new Regulation for Safety of Watercourse Facilities that came into force 1 January 2010. VAV tries to carry out one to two rehabilitation projects each year, and must have assistance from a consultant for engineering design and execution of these projects.
According to the regulation, re-evaluations, flood calculations, dam breach wave calculations and technical plans must be carried out by persons with certified qualifications within the relevant discipline. Re-evaluations are part of VAV's inspection programme, and on average two dams are re-evaluated each year. The flood calculations will be controlled and possibly updated every 15 years.
According to the regulation, re-evaluations, flood calculations, dam breach wave calculations and technical plans must be carried out by persons with certified qualifications within the relevant discipline. Re-evaluations are part of VAV's inspection programme, and on average two dams are re-evaluated each year. The flood calculations will be controlled and possibly updated every 15 years.
Some of the dams have not received dam classification from NVE. Dam classification must be determined before the dams can be re-evaluated or rehabilitated. In many instances a dam breach wave calculation must be performed.
Varighet: 48 måneder
Beskrivelse av fornyelser:
The contracting authority has the right to extend the framework agreement for 2 years + 2 years.
Beskrivelse av opsjoner:
The contracting authority has the right to extend the framework agreement for 2 years + 2 years.
Juridisk, økonomisk, finansiell og teknisk informasjon Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten:
Legally established company
Documentation requirements are in the qualification documentation.
Økonomisk og finansiell stilling:
Sufficient financial capacity to execute the contract.
Documentation requirements are in the qualification documentation.
Teknisk og faglig kapasitet:
Experience is required in accordance with the qualification documentation.
Documentation requirements are in the qualification documentation.
Minste nivå(er) av standarder:
— experience is required with detailed engineering design of dam facilities;
— experience is required with flood calculations and dam breach wave calculations;
— experience is required with inspection of dams, hatches and tunnels and with stabilisation calculations;
— experience is required with detailed engineering design of hatches;
— experience is required with preparation of environmental reports/MOP in relation to temporary draining of magasine.
Informasjon om en bestemt profesjon: Services
Henvisning til relevante bestemmelser i lover og andre forskrifter:
The tenderer will have professional accountability approved for engineering design in all specialist areas in accordance with the Regulation for Safety at Watercourse Facilities (dam safety regulation) PPR 2009-12-18-1600.
Prosedyre
Rettslig grunnlag: 32014L0025
Minste antall kandidater: 4
Største antall kandidater: 6
Objektive kriterier for å velge det begrensede antallet kandidater:
The criteria for selection are in the qualification documentation and tender documents.
Antall deltakere som skal vurderes: 2
Tidspunkt for mottak av tilbud: 12:00
Dato for utsendelse av invitasjoner: 2021-01-27 📅
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 3 måneder