E39 Lyngdal East — Lyngdal West

Nye Veier

The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal Municipality]. The stretch includes:
— approx. 5.3 km open air road,
— approx. 6.4 km tunnel, divided across two tunnel (the Rossås tunnel, 3.7 km,​ and the Kålåst tunnel, 2.7 km)​,
— two longer bridges: Kvelland (over Lygna river) and Hårikstad),
— two motorway junctions with connections to the existing road network.
The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024​.
Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal Municipality.

Frist

Fristen for mottak av tilbud var 2020-10-05. Anskaffelsen ble publisert 2020-09-01.

Leverandører

Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:

Hvem? Hva? Hvor?
Anskaffelseshistorikk
Dato Dokument
2020-09-01 Kunngjøring av konkurranse
2020-09-04 Tilleggsinformasjon
2021-07-10 Kunngjøring om tildeling av kontrakt
Kunngjøring av konkurranse (2020-09-01)
Gjenstand
Anskaffelsens omfang
Tittel: Construction work
Kort beskrivelse:
The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal Municipality]. The stretch includes: — approx. 5.3 km open air road, — approx. 6.4 km tunnel, divided across two tunnel (the Rossås tunnel, 3.7 km,​ and the Kålåst tunnel, 2.7 km)​, — two longer bridges: Kvelland (over Lygna river) and Hårikstad), — two motorway junctions with connections to the existing road network. The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024​. Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal Municipality.
Vis mer
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Bygge- og anleggsarbeid
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsvirksomhet 📦
Tilleggs-CPV: Forberedende anleggsarbeid 📦
Utførelsessted
NUTS-region: Vest-Agder 🏙️

Prosedyre
Prosedyretype: Konkurranse med forhandling
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet

Oppdragsgiver
Identitet
Land: Norge 🇳🇴
Type tildelende myndighet: Offentligrettslig organ
Navn på tildelende myndighet: Nye Veier
Postadresse: Tangen 76
Postnummer: 4608
Poststed: Kristiansand
Kontakt
Internettadresse: http://www.nyeveier.no 🌏
E-post: anskaffelser@nyeveier.no 📧
URL for dokumenter: http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=273726&B=NYEVEIER 🌏
URL for deltakelse: http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=273726&B=NYEVEIER 🌏

Referanse
Datoer
Sendt dato: 2020-09-01 📅
Innleveringsfrist: 2020-10-05 📅
Publiseringsdato: 2020-09-04 📅
Startdato: 2021-05-28 📅
Sluttdato: 2024-12-31 📅
Identifikatorer
Kunngjøringsnummer: 2020/S 172-416953
OJ-S-utgave: 172
Tilleggsinformasjon
Compensation for participation in step 2 (the Tender Phase): Tenderers selected for step 2 and who participate without being awarded a contract can demand compensation of NOK 6 million for their participation. Further terms are in the contest provision in the tender management tool.
Vis mer

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal Municipality]. The stretch includes:
Vis mer
— approx. 5.3 km open air road,
— approx. 6.4 km tunnel, divided across two tunnel (the Rossås tunnel, 3.7 km,​ and the Kålåst tunnel, 2.7 km)​,
— two longer bridges: Kvelland (over Lygna river) and Hårikstad),
— two motorway junctions with connections to the existing road network.
The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024​.
Vis mer
Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal Municipality.
Estimert totalverdi: 3 000 000 000 NOK 💰
Kort beskrivelse:
In step 2 (the tender phase) the contracting authority will implement individual meetings with tenderers in order to get confirmation of the builder’s maximum price (BMP), deadlines and any uncertainties in the tender documentation. The contracting authority will have the opportunity to make minor adjustments, necessary supplementation and/or clarification on the background of the individual meetings.
Vis mer
Part of the detailed regulation plan for E39 Herdal-Røyskår has been appealed by the Norwegian Public Roads Administration. The outcome is not known at the time of this notice. The contracting authority therefore reserves the right to extend the tender phase (Step 2) in the event of postponement.
Vis mer
Estimert verdi eksklusive mva: 3 000 000 000 NOK 💰
Beskrivelse av opsjoner:
Alternative solutions for work packages in the tender documentation and possible options for optimisation.
Tilleggsinformasjon:
Compensation for participation in step 2 (the Tender Phase):
Tenderers selected for step 2 and who participate without being awarded a contract can demand compensation of NOK 6 million for their participation. Further terms are in the contest provision in the tender management tool.
Utførelsessted
Hovedsted eller utførelsessted: Lyngdal.

Juridisk, økonomisk, finansiell og teknisk informasjon
Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten: See the requirements/criteria for qualification in the tender management tool.
Økonomisk og finansiell stilling: See the requirements/criteria for qualification in the tender management tool.
Minste nivå(er) av standarder: See the requirements/criteria for qualification in the tender management tool.
Teknisk og faglig kapasitet: See the requirements/criteria for qualification in the tender management tool.
Kontraktutførelse
Vilkår for kontraktoppfyllelse:
In chapter C3 of the contract there are special contract provisions related to health, environment and safety (HSE), including the requirement for systematic HSE work, traffic safety, Outer Environment, CEEQUAL certification and other detailed requirements for execution.
Vis mer
Furthermore, the contracting authority refers to requirements/criteria concerning qualification in the tender management tool.

Prosedyre
Rettslig grunnlag: 32014L0024
Minste antall kandidater: 3
Største antall kandidater: 5
Objektive kriterier for å velge det begrensede antallet kandidater:
Assessment of reference projects:
B1 (weighting 80 %): relevance of three site project references;
B2 (weighting 20 %): relevance for two engineering design references.
The three to five tenderers who achieve the highest total score on the should-requirements will be invited to submit a tender in stage 2 (the tender phase). The contracting authority will decide the final number of tenderers who will be invited to stage 2. If there is not a minimum of three qualified tenderers, the contracting authority reserves the right to invite two tenderers to step 2, cf. PPR § 16-12 (3).
Vis mer
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: engelsk 🗣️
norsk 🗣️
Tilbudets gyldighetsperiode: 2021-09-01 📅
Tildelingskriterier
Kvalitetskriterium (navn): K1 Performance justification
Kvalitetskriterium (vekting): 25 %
Kvalitetskriterium (navn): K2 Risk assessment
Kvalitetskriterium (vekting): 15 %
Kvalitetskriterium (navn): K3 Optimisation
Kvalitetskriterium (vekting): 10 %
Kvalitetskriterium (navn): K4 Competence and experience of key personnel
Kvalitetskriterium (vekting): 20 %
Pris (vekting): 30 %

Oppdragsgiver
Identitet
Nasjonalt registreringsnummer: 915 488 099
Kontakt
Kontaktpunkt: Ruben Ramsland
Internettadresse: www.nyeveier.no 🌏
Adresse til kjøperprofilen: https://eu.eu-supply.com/ctm/Company/CompanyInformation/Index/279098 🌏
URL for dokumenter: http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=273726&B=NYEVEIER 🌏

Utfyllende informasjon
Klageinstans
Navn: Kristiansand Tingrett
Postadresse: Tollbodgata 45
Poststed: Kristiansand
Postnummer: 4614
Land: Norge 🇳🇴
Internettadresse: https://www.domstol.no/Enkelt-domstol/kristiansand-tingrett/ 🌏
Organ ansvarlig for meklingsprosedyrer
Navn: Klagenemnda for Offentlige Anskaffelse
Postadresse: Zander Kaaes gate 7
Poststed: Bergen
Postnummer: 5015
Internettadresse: http://www.kofa.no 🌏
Tjeneste hvor informasjon om klageprosedyren kan innhentes
Navn: Nye Veier AS
Postadresse: Tangen 76
Postnummer: 4608
E-post: anskaffelser@nyeveier.no 📧
Kilde: OJS 2020/S 172-416953 (2020-09-01)
Tilleggsinformasjon (2020-09-04)
Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal municipality]. The stretch includes: — Approx. 2.5 km open air road — Approx. 6.1 km tunnel works, divided between two tunnels (the Rossås tunnel, 3.4 km, and the Kålås tunnel, 2.7 km) — Two long bridges: Kvelland (over Lygna river) and Hårikstad, 170 m, — Two motorway junctions with connections to the existing road network. The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024. Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal municipality.
Vis mer
Metadata for kunngjøring
Dokumenttype: Tilleggsinformasjon
Felles innkjøpsordliste (CPV)
Kode: Byplanleggings- og landskapsarkitekttjenester 📦

Referanse
Datoer
Sendt dato: 2020-09-04 📅
Publiseringsdato: 2020-09-09 📅
Identifikatorer
Kunngjøringsnummer: 2020/S 175-423847
Refererer til kunngjøring: 2020/S 172-416953
OJ-S-utgave: 175

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal municipality]. The stretch includes:
Vis mer
— Approx. 2.5 km open air road
— Approx. 6.1 km tunnel works, divided between two tunnels (the Rossås tunnel, 3.4 km, and the Kålås tunnel, 2.7 km)
— Two long bridges: Kvelland (over Lygna river) and Hårikstad, 170 m,
— Two motorway junctions with connections to the existing road network.
The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024.
Vis mer
Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal municipality.
Kilde: OJS 2020/S 175-423847 (2020-09-04)
Kunngjøring om tildeling av kontrakt (2021-07-10)
Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
The contract work includes turnkey contracts for engineering design, construction of and warranty responsibility for a new four-lane motorway between the Herdalen junction and Røyskår junction in Lyngdal kommune [Lyngdal municipality]. The stretch includes: — approx. 5.3 km open air road; — approx. 6.4 km tunnel, divided across two tunnel (the Rossås tunnel, 3.7 km,​ and the Kålåst tunnel, 2.7 km)​; — two longer bridges: Kvelland (over Lygna river) and Hårikstad; — two motorway junctions with connections to the existing road network. The contract is based on NS 8407:2011 with fixed price and includes an introductory phase with optimisation and preparation. The builder’s maximum price (BMP) for the contract work including warranty responsibility, excluding options and VAT, amounts to NOK 2 750 000 000. Planned construction start is in the third quarter 2021 with completion in 2024​. Refer to ‘Detailed Regulation Plan E39 Herdal-Røyskår’ adopted 18 June 2020 by Lyngdal municipality.
Vis mer
Totalverdi for anskaffelsen: 2 900 000 000 NOK 💰
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
Utførelsessted
NUTS-region: Norge 🏙️

Prosedyre
Tilbudstype: Ikke aktuelt

Oppdragsgiver
Identitet
Postadresse: Kjøita 6
Postnummer: 4630

Referanse
Datoer
Sendt dato: 2021-07-10 📅
Publiseringsdato: 2021-07-15 📅
Identifikatorer
Kunngjøringsnummer: 2021/S 135-358213
OJ-S-utgave: 135
Tilleggsinformasjon
Compensation for participation in step 2 (the Tender Phase): Tenderers selected for step 2 and who participate without being awarded a contract can demand compensation of NOK 6 000 000 for their participation. Further terms are in the contest provisions in the tender management tool.
Vis mer

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
— approx. 5.3 km open air road;
— approx. 6.4 km tunnel, divided across two tunnel (the Rossås tunnel, 3.7 km,​ and the Kålåst tunnel, 2.7 km)​;
— two longer bridges: Kvelland (over Lygna river) and Hårikstad;
Tilleggsinformasjon:
Tenderers selected for step 2 and who participate without being awarded a contract can demand compensation of NOK 6 000 000 for their participation. Further terms are in the contest provisions in the tender management tool.

Tildeling av kontrakt
Dato for kontraktinngåelse: 2021-07-02 📅
Navn: JV Implenia Stangeland E39 Lyngdal ANS
Postadresse: Fornebuveien 11
Poststed: Lysaker
Postnummer: 1366
Land: Norge 🇳🇴
Telefon: +47 22507300 📞
E-post: susann.lillehagen@implenia.com 📧
Internettadresse: http://www.implenia.no 🌏
Totalverdi for anskaffelsen: 2 900 000 000 NOK 💰
Informasjon om tilbud
Antall mottatte tilbud: 3

Utfyllende informasjon
Klageinstans
Navn: Agder tingrett
Postadresse: Postboks 63
Postnummer: 4661
Internettadresse: https://www.domstol.no/enkelt-domstol/agder-tingrett/ 🌏
Organ ansvarlig for meklingsprosedyrer
Navn: Klagenemnda for offentlige anskaffelse
Tjeneste hvor informasjon om klageprosedyren kan innhentes
Postadresse: Kjøita 6
Postnummer: 4630
Kilde: OJS 2021/S 135-358213 (2021-07-10)