County Road 500 Folgefonn Tunnel – Årsnes, tunnel and road improvement

Vestland fylkeskommune

Fv [County Road] 500 the Folefonn Tunnel — Årsnes, in Kvinnherad municipality there is a 22 km stretch where approximately an avalanche protection tunnel of approximately 1 500 meters will be built at Kroka. In addition, selected parcels of the stretch will be improved and the road width will be increased. This is to increase accessibility and traffic safety along the stretch.

Frist

Fristen for mottak av tilbud var 2019-12-04. Anskaffelsen ble publisert 2019-11-04.

Hvem? Hva? Hvor?
Anskaffelseshistorikk
Dato Dokument
2019-11-04 Kunngjøring av konkurranse
Kunngjøring av konkurranse (2019-11-04)
Gjenstand
Anskaffelsens omfang
Tittel: Construction work
Referansenummer: 19/272160
Kort beskrivelse:
Fv [County Road] 500 the Folefonn Tunnel — Årsnes, in Kvinnherad municipality there is a 22 km stretch where approximately an avalanche protection tunnel of approximately 1 500 meters will be built at Kroka. In addition, selected parcels of the stretch will be improved and the road width will be increased. This is to increase accessibility and traffic safety along the stretch.
Vis mer
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Bygge- og anleggsarbeid
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsvirksomhet 📦
Tilleggs-CPV: Bygge- og anleggsarbeid i forbindelse med Veitunnel 📦
Utførelsessted
NUTS-region: Hordaland 🏙️

Prosedyre
Prosedyretype: Konkurransepreget dialog
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet

Oppdragsgiver
Identitet
Land: Norge 🇳🇴
Type tildelende myndighet: Regional eller lokal myndighet
Navn på tildelende myndighet: Vestland fylkeskommune
Postadresse: Agnes Mowinckels gate 5
Postnummer: 5008
Poststed: Bergen
Kontakt
Internettadresse: http://vlfk.no 🌏
E-post: kathrine.lono.lahlum@vegvesen.no 📧
URL for dokumenter: https://tendsign.no/public/list_public_publications.aspx?FromPublic=true&OrganizationID=500203274 🌏
URL for deltakelse: https://tendsign.no/doc.aspx?UniqueId=afzzyctkjt&GoTo=Tender 🌏

Referanse
Datoer
Sendt dato: 2019-11-04 📅
Innleveringsfrist: 2019-12-04 📅
Publiseringsdato: 2019-11-06 📅
Startdato: 2020-03-02 📅
Identifikatorer
Kunngjøringsnummer: 2019/S 214-526510
OJ-S-utgave: 214
Tilleggsinformasjon
The tender conference will take place in Sundal on the 15.11.2019, 10.00 a.m. Register for the tender conference by the 8.11.2019 to the project manager, Kathrine Løno Lahlum: Email: kathrine.lono.lahlum@vegvesen.no or Haakon Innset email: haakon.innset@vegvesen.no
Vis mer

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
Fv [County Road] 500 the Folefonn Tunnel — Årsnes, in Kvinnherad municipality there is a 22 km stretch where approximately an avalanche protection tunnel of approximately 1 500 meters will be built at Kroka. In addition, selected parcels of the stretch will be improved and the road width will be increased. This is to increase accessibility and traffic safety along the stretch.
Vis mer
The avalanche protection tunnel at the Kroka parcel:
The tunnel (including portals) will be approx. 1 500 m and the implementation includes electrical and safety equipment in the tunnel. The total parcel length is approx. 1 900 m. The contractor must also anticipate operation of the tunnel, both electrical and roads, up until formal hand-over is completed (deadline).
Vis mer
The zoning plan for this parcel is under preparation.
The avalanche protection project will build on the zoning plan and zoning provisions, that are anticipated to be undertaken by Kvinnherad municipality in the fourth quarter of 2020.
Road expansion along the Folgefonn Tunnel — Årsnes stretch:
The current road has varying standards and widths and is located along the Mauranger Fjord. There is a need for different measures along the stretch with i.a. width expansion, improvement of the carrying capacity, improved drainage, curve improvement and new surface. The project places emphasis on the reuse of excess masses from the tunnel for road and curve improvement. Filling mass deposited at sea will be carried out in-line with the applicable regulations. The County Governor in Vestland is the authority here. Zoning plan processes have not started for the actual stretches for filling at sea. In connection with this work, there may be a need for voluntary contracts with landowners.
Vis mer
Model-based engineering design:
The contractor will be involved in the engineering design, but will do so in collaboration with the builder. BIM (Building Information Modelling) will be a joint work platform for this interaction. Through the joint BIM model, we will seek to ensure that all of the project participants work in-line and have good cross-discipline insight, at the same time that the builder gets insight at any given time. In parallel with this, the building must control the planning process according to the planning and construction act. The contractor will be involved early in the project. The objective is to utilise the combined competence of the parties and to achieve a better end product.
Vis mer
The contractor will thereafter implement the construction of the tunnel and improvement of the road stretch, but in this phase the interaction between the parties will also continue.
Tilleggsinformasjon:
The tender conference will take place in Sundal on the 15.11.2019, 10.00 a.m.
Register for the tender conference by the 8.11.2019 to the project manager, Kathrine Løno Lahlum:
Utførelsessted
Hovedsted eller utførelsessted:
The stretch, County Road 500 the Folgefonn Tunnel — Årsnes in Kvinnherad municipality.

Juridisk, økonomisk, finansiell og teknisk informasjon
Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten: See the tender documentation B2-2 qualification requirement.
Økonomisk og finansiell stilling: See the tender documentation B2-2 qualification requirement.
Teknisk og faglig kapasitet: See the tender documentation B2-2 qualification requirement.
Kontraktutførelse
Vilkår for kontraktoppfyllelse:
See the tender documentation chapter C:
C Contract provisions — NS 8407:2011.
C1 General contract provisions.
C2 Special contractual provisions for construction, the Norwegian National Roads Administration.
C3 Contract Document.
C4 Contract for the implementation phase.
C5 Third party contract.

Prosedyre
Rettslig grunnlag: 32014L0024
Gjeldende anskaffelsesrett: Statens Vegvesen [The Norwegian Public Roads Administration]
Minste antall kandidater: 3
Største antall kandidater: 4
Objektive kriterier for å velge det begrensede antallet kandidater: See B2, competence rules in the tender documentation.
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 2020-05-11 📅

Oppdragsgiver
Identitet
Nasjonalt registreringsnummer: 821 311 632
Navn på tildelende myndighet: Statens vegvesen
Nasjonalt registreringsnummer: 971 032 081
Poststed: Leikanger
Land: Vestlandet 🏙️
Kontakt
Kontaktpunkt: Kathrine Løno Lahlum
E-post: kathrine.lono.lahlum@vegvesen.no 📧
URL for dokumenter: https://tendsign.no/public/list_public_publications.aspx?FromPublic=true&OrganizationID=500203274 🌏

Referanse
Tilleggsinformasjon
Visma notice: https://opic.com/id/afzzyctkjt

Utfyllende informasjon
Klageinstans
Navn: Hordaland fylkeskommune
Poststed: Bergen
Land: Norge 🇳🇴
Kilde: OJS 2019/S 214-526510 (2019-11-04)