PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6. Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21. A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also water and sewage pipelines in full operation. On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21. PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d The casting parts in the station are delivered by ‘Teknikke entreprisen’ and close coordinating is necessary.
Frist
Fristen for mottak av tilbud var 2019-01-14.
Anskaffelsen ble publisert 2018-12-05.
Kunngjøring av konkurranse (2018-12-05) Gjenstand Anskaffelsens omfang
Tittel: Construction work
Kort beskrivelse:
PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also water and sewage pipelines in full operation.
On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21.
PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d
The casting parts in the station are delivered by ‘Teknikke entreprisen’ and close coordinating is necessary.
PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also water and sewage pipelines in full operation.
On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21.
PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d
The casting parts in the station are delivered by ‘Teknikke entreprisen’ and close coordinating is necessary.
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Bygge- og anleggsarbeid
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS)
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsvirksomhet📦 Utførelsessted
NUTS-region: Akershus
🏙️
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also water and sewage pipelines in full operation.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also water and sewage pipelines in full operation.
On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21.
PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d
The casting parts in the station are delivered by ‘Teknikke entreprisen’ and close coordinating is necessary.
Estimert totalverdi: 10 000 000 NOK 💰
Kort beskrivelse:
Site works and construction works for the construction of a large pressure boosting station for main water supply.
Estimert verdi eksklusive mva: 10 000 000 NOK 💰
Utførelsessted
Hovedsted eller utførelsessted: By Hexebergveien North of Frogner in Sørum municipality.
Juridisk, økonomisk, finansiell og teknisk informasjon Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten: See the tender documents.
Kontraktutførelse
Vilkår for kontraktoppfyllelse: See the tender documents.
Prosedyre
Rettslig grunnlag: 32014L0024
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 3 måneder
Dato for åpning av tilbud: 2019-01-14 📅
Tidspunkt for åpning av tilbud: 14:00
Tilleggsinformasjon: Closed.
Oppdragsgiver Identitet
Nasjonalt registreringsnummer: 992 110 996
Annen type oppdragsgiver: Inter-municipal company
Kontakt
Kontaktpunkt: Henrik Stokkebekk
Adresse til kjøperprofilen: http://www.nrva.no/🌏
URL for dokumenter: https://permalink.mercell.com/96021460.aspx🌏
Tilleggsinformasjon (2018-12-18) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also Water & Sewage pipelines in full operation.
On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21.
PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d
PV 21 will be constructed by Esval, which is located by Heksebergveien just north of where it crosses under the E6.
Previously, a large valve shaft (K5504) with an avalanche cover, was built just south of the placement of PV21. From K5504, a 600 mm pipe socket has been laid, which continues in a 710 mm PE pipeline. Also, a 710 PE pipeline must be lain for connection to the flange exterior wall PV21.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also Water & Sewage pipelines in full operation.
On the other end of PV21, the pipeline that crosses Leira is connected to (pp mm PE). It is ready for connection north of the station and will be connected by the contractor who carried out the boring, toward the flange on the outside of PV 21.
PV21 will be founded on piles to rock. In PV 21 there is a tube boiler that is smaller than the rest of the building.d
Metadata for kunngjøring
Dokumenttype: Tilleggsinformasjon
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also Water & Sewage pipelines in full operation.
A pipeline installation has been lain from K5504 and in a an arch around the placement of PV21 in order to make place for this. This pipeline system is in full operation. Along Heksebergveien, there are also Water & Sewage pipelines in full operation.