Nordby tunnel was opened in 1992 with two tunnels, each with 2 lanes in the same direction. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3,850 metres. Smiehagen tunnel was opened in 1999 with one tunnel with two lanes in one direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres. The work involves a complete renovation of Nordby and Smeihage tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Norby sough — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones. The work shall primarily be carried out on one lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
Frist
Fristen for mottak av tilbud var 2017-05-29.
Anskaffelsen ble publisert 2017-04-11.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2017-04-11) Gjenstand Anskaffelsens omfang
Tittel: Construction work
Kort beskrivelse:
Nordby tunnel was opened in 1992 with two tunnels, each with 2 lanes in the same direction. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3,850 metres.
Smiehagen tunnel was opened in 1999 with one tunnel with two lanes in one direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihage tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Norby sough — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on one lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
Nordby tunnel was opened in 1992 with two tunnels, each with 2 lanes in the same direction. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3,850 metres.
Smiehagen tunnel was opened in 1999 with one tunnel with two lanes in one direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihage tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Norby sough — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on one lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Nordby tunnel was opened in 1992 with two tunnels, each with 2 lanes in the same direction. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3,850 metres.
Smiehagen tunnel was opened in 1999 with one tunnel with two lanes in one direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihage tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Norby sough — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work involves a complete renovation of Nordby and Smeihage tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Norby sough — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on one lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
Estimert totalverdi: 250 000 000 NOK 💰
Kort beskrivelse:
The Norwegian Public Roads Administration, Eastern Region, has an owner, rented or leased contract for more than 80 000 m2, split between more than 140 buildings in Oppland, Hedmark, Akershus, Oslo and Østfold counties, from Tyin to Svinesund. As a part of the professionalisation of the management and operation of these buildings, we need for one or several framework agreements for the following services: Trade services, technical disciplines and operational services for all 140 buildings.
The Norwegian Public Roads Administration, Eastern Region, has an owner, rented or leased contract for more than 80 000 m2, split between more than 140 buildings in Oppland, Hedmark, Akershus, Oslo and Østfold counties, from Tyin to Svinesund. As a part of the professionalisation of the management and operation of these buildings, we need for one or several framework agreements for the following services: Trade services, technical disciplines and operational services for all 140 buildings.
Varighet: 17 måneder Utførelsessted
Hovedsted eller utførelsessted: Vestby, Norway.
Prosedyre
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 2017-08-29 📅
Dato for åpning av tilbud: 2017-05-29 📅
Tidspunkt for åpning av tilbud: 12:15
Sted: Not open to the public.
A winner of the competition will not be announced before the evaluation has taken place.
Utfyllende informasjon Klageinstans
Navn: Statens vegvesen region øst
Poststed: Oslo
Land: Norge 🇳🇴
E-post: thomas.kalleberg@vegvesen.no📧
Kilde: OJS 2017/S 074-144089 (2017-04-11)
Tilleggsinformasjon (2017-04-19) Gjenstand Metadata for kunngjøring
Dokumenttype: Tilleggsinformasjon
Kunngjøring om tildeling av kontrakt (2017-11-08) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The Nordby tunnel was opened in 1992 with a 2 tunnel courses, each with 2 lanes in the opposite directions. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3 850 metres.
Smiehagen tunnel was opened in 1999 with 1 tunnel with 2 lanes in 1 direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihagen tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Nordby south — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on 1 lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
The Nordby tunnel was opened in 1992 with a 2 tunnel courses, each with 2 lanes in the opposite directions. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3 850 metres.
Smiehagen tunnel was opened in 1999 with 1 tunnel with 2 lanes in 1 direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihagen tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Nordby south — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on 1 lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
Totalverdi for anskaffelsen: 385 299 976 NOK 💰
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
The Nordby tunnel was opened in 1992 with a 2 tunnel courses, each with 2 lanes in the opposite directions. The tunnels has 5 technical rooms, of which 3 are located in the tunnel. The tunnel's total length is 3 850 metres.
Smiehagen tunnel was opened in 1999 with 1 tunnel with 2 lanes in 1 direction. The tunnel has a technical room that is located in the open air (above the tunnel). The tunnel's total length is 892 metres.
The work involves a complete renovation of Nordby and Smeihagen tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Nordby south — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work involves a complete renovation of Nordby and Smeihagen tunnels on the E6 in Follo. In addition there is approx. 6.6 km of work in open air zones (Nordby north — Ringnes, called Vinterbrosletta 2.1 km); Nordby south — Smeihagen 0.8 km; Smiehagen south — Korsegården 3.7 km. Portals and signs with the accompanying ditches shall be established in the open air zones.
The work shall primarily be carried out on 1 lane at a time, with traffic in the other lane. The work in the open air and in the tunnel shall mainly be carried out at night, with the exception of 2 closure periods of a total of 5 months.
The renovation of the Nordby and Smiehagen tunnel.
The expansion for 3 technical rooms in the Nordby tunnel, of which 1 350 m
The expansion of 3 technical rooms outside the tunnels (open-air zones)
All electrical technical equipment shall be replaced:
— New ventilation systems in both tunnels.
Rock protection systems behind arches.
Fire protection measures in tunnel rooms and smoke protection measure for emergency ways.
Utførelsessted
Hovedsted eller utførelsessted: Ski/Ås/Frogn.