The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed. Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included. The stretch is approx. 1 250 m long. A new road light system shall be established. A new water and sewage system and a drainage and storm water run-off system shall be established. A continuous cable system in the plant must be considered. Some light filling with foam glass. Demolition of garages. The establishment of temporary parking lots and storage containers. Challenging traffic management. The average annual daily traffic/AADT is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected. The project will be implemented model-based.
Frist
Fristen for mottak av tilbud var 2018-01-26.
Anskaffelsen ble publisert 2017-11-24.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2017-11-24) Gjenstand Anskaffelsens omfang
Tittel: Construction work
Referansenummer: 17/132951
Kort beskrivelse:
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included.
The stretch is approx. 1 250 m long. A new road light system shall be established.
A new water and sewage system and a drainage and storm water run-off system shall be established.
A continuous cable system in the plant must be considered.
Some light filling with foam glass.
Demolition of garages. The establishment of temporary parking lots and storage containers.
Challenging traffic management. The average annual daily traffic/AADT
is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
The project will be implemented model-based.
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included.
The stretch is approx. 1 250 m long. A new road light system shall be established.
A new water and sewage system and a drainage and storm water run-off system shall be established.
A continuous cable system in the plant must be considered.
Some light filling with foam glass.
Demolition of garages. The establishment of temporary parking lots and storage containers.
Challenging traffic management. The average annual daily traffic/AADT
is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
The project will be implemented model-based.
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Bygge- og anleggsarbeid
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsvirksomhet📦
Tilleggs-CPV: Bygge- og anleggsvirksomhet📦 Utførelsessted
NUTS-region: Akershus
🏙️
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Laveste pris
We encourage all interested parties to participate in the tender conference that will take place at the Norwegian Public Roads Administration Eastern Region, 20.12.2017 (9:00). Address: Østensjøveien 34, Oslo.
Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included.
The stretch is approx. 1 250 m long. A new road light system shall be established.
A new water and sewage system and a drainage and storm water run-off system shall be established.
A continuous cable system in the plant must be considered.
Some light filling with foam glass.
Demolition of garages. The establishment of temporary parking lots and storage containers.
Challenging traffic management. The average annual daily traffic/AADT
is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
The project will be implemented model-based.
Estimert totalverdi: 100 000 000 NOK 💰
Kort beskrivelse:
Subject to funding:
When the tender notice is published a final decision on funding for the project has not yet been made. If the funding is not approved, the tender contest will be cancelled.
Other:
Estimert verdi eksklusive mva: 100 000 000 NOK 💰
Tilleggsinformasjon:
We encourage all interested parties to participate in the tender conference that will take place at the Norwegian Public Roads Administration Eastern Region, 20.12.2017 (9:00). Address: Østensjøveien 34, Oslo.
Juridisk, økonomisk, finansiell og teknisk informasjon Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten: As described in the tender documentation.
Økonomisk og finansiell stilling: As described in the tender documentation.
Minste nivå(er) av standarder: As described in the tender documentation.
Teknisk og faglig kapasitet: As described in the tender documentation.
Kontraktutførelse
Vilkår for kontraktoppfyllelse: As described in the tender documentation.
Prosedyre
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 2018-04-25 📅
Dato for åpning av tilbud: 2018-01-26 📅
Tidspunkt for åpning av tilbud: 12:00
Tilleggsinformasjon:
Not a traditional opening of tenders. This project is executed as one of several pilot projects for submitting electronic tenders to the Norwegian Public Roads Administration, the Eastern Region.
An opening protocol will be published in the CTM (Complete Tender Management system) after the tender deadline has expired.
Utfyllende informasjon Klageinstans
Navn: Statens vegvesen Region øst
Postadresse: Postboks 1010 Nordre Ål
Poststed: Lillehammer
Postnummer: 2605
Land: Norge 🇳🇴
Kilde: OJS 2017/S 228-476323 (2017-11-24)
Kunngjøring om tildeling av kontrakt (2018-03-08) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included.
The stretch is approx. 1,250 m long. A new road light system shall be established.
A new water and sewage system and a drainage and storm water run-off system shall be established.
A continous cable system in the plant must be considered.
Some light filling with foam glass.
Demolition of garages. The establishment of temporary parking lots and storage containers.
Challenging traffic management. The average annual daily traffic / AADT is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
The project will be implemented model-based.
The project includes the development of a two-sided cycle lane as well as a one-sided pavement. Exit roads and side roads shall be adapted to the new traffic situation. The current retaining walls along the north side of Prof. Kohts shall be replaced. New retaining walls along the south side shall be constructed.
Cast-on-site walls and stacking walls with soil reinforcement shall be constructed. Piling under wall S1 is included.
The stretch is approx. 1,250 m long. A new road light system shall be established.
A new water and sewage system and a drainage and storm water run-off system shall be established.
A continous cable system in the plant must be considered.
Some light filling with foam glass.
Demolition of garages. The establishment of temporary parking lots and storage containers.
Challenging traffic management. The average annual daily traffic / AADT is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
The project will be implemented model-based.
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
We encourage all interested parties to participate in the tender conference that will take place at the Norwegian Public Roads Administration Eastern Region, 20.12.2017 (09:00). Address: Østensjøveien 34, Oslo.
Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The stretch is approx. 1,250 m long. A new road light system shall be established.
A continous cable system in the plant must be considered.
Challenging traffic management. The average annual daily traffic / AADT is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
Challenging traffic management. The average annual daily traffic / AADT is 2,800, many cyclists. In periods the entire road or parts of the road are expected to be closed (the properties shall always have access) Control by traffic lights must be expected.
Tilleggsinformasjon:
We encourage all interested parties to participate in the tender conference that will take place at the Norwegian Public Roads Administration Eastern Region, 20.12.2017 (09:00). Address: Østensjøveien 34, Oslo.
Tildeling av kontrakt
Dato for kontraktinngåelse: 2018-03-07 📅
Kilde: OJS 2018/S 049-109672 (2018-03-08)