2019-02-15   P.109 Storanipa Outside Area and Landscape Work (Fjell VAR as)
A new main treatment facility is being constructed in rock, and a new administration building has been established in the outside area. A car park, site for cabin refuse disposal, road barrier, street lights, etc., are to be developed around this and in parts of the roughly levelled area of approximately 5 000–6 000 m. A contractor will therefore be contracted for completing this LARK work. The work is described as a turnkey contract based on the attached set-up and drawings. The attached complete tender … Vis anskaffelsen »
2019-01-29   P.109 HRA Storanipa Contract S 01 — Submarine Pipelines (Fjell VAR as)
This request consists of 3 section: Part I: Procurement of PE pipelines; Part II: Procurement of bolt free load weights and procurement of execution contracts. A total of approx. 2 440 lineal metres of pipeline will be delivered, distributed over 2 pipelines with PE 100 SDR 11 dim630 pipelines in the sea. These are emission pipelines from the new treatment plant in Storanipa. These are to be lain from approx. contour -5 to approx. contour -70 metres. Vis anskaffelsen »
2018-07-05   124 Storskaret — Lonavegen main sewage pipeline (Fjell VAR as)
New sewage pipelines are to be laid and a water pipeline with the accompanying manholes between Storskaret and Lonavegen at Straume in Fjell municipality. The work will be carried out on and by public roads that will be open throughout the site period. There will be strict safety requirements for the Contractor. Vis anskaffelsen »
2018-07-03   P.109 HRA Storanipa — contract A1 — Turnkey Contract ADM. Building (Fjell VAR as)
FjellVAR AS is constructing a new main treatment facility for sewage in rock and a free-standing administration building is to be constructed in prefabricated concrete elements on a ready compressed stone filling outside the rock installation. The building is to be constructed with 1 floor, the outer walls from concrete elements, and a flat hollow roof that is insulated and covered. The building is to be constructed as a turnkey contract with handover by the architect. Vis anskaffelsen »
2016-12-20   HRA Storanipa — Contract F2 (Fjell VAR as)
This qualification documentation concerns work with blasting, loading up and transport of rock fragments from treatment halls and tunnels in connection with the establishment of rock halls for HRA Storanipa. Vis anskaffelsen »
2016-11-19   HRA Storanipa — contract P1 — prequalification consultant (Fjell VAR as)
This qualification documentation is for engineering design services for the construction work, HVAC, electro, fire and heating, water and sewage installations for the construction of a new main sewage treatment facility at Våge in Fjell municipality. Vis anskaffelsen »
2016-06-10   Open tender contest LAN parts 1 and 3 of the regulations (Fjell VAR as)
The procurement is for a Loan of 180 000 000 NOK with a municipal guarantee. Vis anskaffelsen »
2016-04-19   HRA Storanipa — pre-qualification turnkey contract machine and process, contract M1 (Fjell VAR as)
This notice is for a pre-qualification for turnkey contract M1, which comprises planning, engineering design services, delivery and assembly of technical machinery and process equipment for the treatment facility. Vis anskaffelsen »
2014-01-29   Engagement as a builder consultant in establishing new main sewage treatment plant for FjellVAR a/s (Fjell VAR as)
Fjell Municipality has its own municipality plan for water and sewage 2011–2022 with a decision to build a new main sewer treatment plant for the communities of Litle Sotra - Bildøy - Morlandstø.Following the investigation period 28.11.2013, the Fjell Municipality Council decided to locate the facility in the mountains, specifically in Storanipa, Våge on Litle Sotra. FjellVAR a/s is 100 % owned by the municipality of Fjell, which will stand as the builder of the plant and its operator after completion. … Vis anskaffelsen »
2012-10-19   Loan (Fjell VAR as)
FjellVAR AS requests tenders for a serial loan of 150 000 000 NOK for financing approved investments in the period 2012-2013. 30 year repayment period. Interest: Floating interest connected to NIBOR 3 months interest set 2 bank days before the start of the calculation period. NIBOR noted on Reuters at 12:00 on the relevant day. NOTE: To register your interest in this notice and obtain any additional information please visit the Doffin Web Site at http://www.doffin.no/Search/Search_Switch.aspx?ID=270894. Vis anskaffelsen »
Nevnte leverandører: Klp Banken