Innskudd og garantier som kreves
Generally, the successful tenderer will be asked to provide the Performance
guarantees of 5% of the amount of the Contract and the Pre-Financing Guarantee
for the full amount of pre-payment at the signing of the Contract. The Contracting
Authority reserves the right to waive the Pre-Financing Guarantee requirements, if
the Contractor does not require the advance payment for the works. In this case,
the Contractor bears responsibility to implement the contract using their own
means. A 100% payment will be made to the contractor by the Contracting Authority
upon the delivery and provisional acceptance of the goods. For a minor contract (≤
NOK 200 000), the Contracting Authority, depending on its assessment of the risks,
may decide to waive the Performance Guarantee requirement. In this case, the deci-sion will take into consideration the tenderer’s litigation history, available resources and means, previously implemented contracts, etc. Within twenty (20) calendar days after receipt of the Contract the successful tenderer shall sign the Contract and return it to the Contracting Authority along with
a corresponding Pre-Financing and Performance Guarantees, if required.
Where the successful tenderer fails to sign the Contract or furnish a corresponding
Pre-Financing and Performance Guarantees, if required, within thirty (30) calendar
days after the Letter of Acceptance and receipt of the Contract, the Contracting
Authority shall have the right to deem the award of contract null and void. In the
event of avoidance of the award of contract the Contract-ing Authority shall refer to
the next successful tenderer.