The competition is for the delivery of a turnkey contract with interaction for the renovation of Nesoddtangen primary school and the community centre, expansion of the school with a new building and a new multi-purpose hall. The assignment also includes the demolition of the existing gym building and development of outside areas. The project shall be carried out with the school in operation at the school and a secure school road throughout the entire construction period. The procurement shall cover the contracting authority ́s need for a turnkey contractor, with his contractual partners for engineering design, renovation/construction and trial operation of the primary school. Subject to political approval, re-regulation, economic coverage and other factual reasons, Nesodden municipality intends to enter into a partnering contract with the winner of the competition. The procurement ́s value (contract cost) is estimated to be NOK 250,000,000 excluding VAT. The volume is an estimate and is not binding for the contracting authority. It is up to the parties to plan and carry out the project so that the cost frame is not exceeded. See the procurement documents for further information.
Frist
Fristen for mottak av tilbud var 2025-03-11.
Anskaffelsen ble publisert 2025-02-04.
Kunngjøring av konkurranse (2025-02-04) Gjenstand Anskaffelsens omfang
Tittel: Renovation of Nesoddtangen primary school and a new multi-purpose hall, partnering contract
Referansenummer: 24017
Kort beskrivelse:
The competition is for the delivery of a turnkey contract with interaction for the renovation of Nesoddtangen primary school and the community centre, expansion of the school with a new building and a new multi-purpose hall. The assignment also includes the demolition of the existing gym building and development of outside areas. The project shall be carried out with the school in operation at the school and a secure school road throughout the entire construction period.
The procurement shall cover the contracting authority ́s need for a turnkey contractor, with his contractual partners for engineering design, renovation/construction and trial operation of the primary school.
Subject to political approval, re-regulation, economic coverage and other factual reasons, Nesodden municipality intends to enter into a partnering contract with the winner of the competition.
The procurement ́s value (contract cost) is estimated to be NOK 250,000,000 excluding VAT. The volume is an estimate and is not binding for the contracting authority. It is up to the parties to plan and carry out the project so that the cost frame is not exceeded.
See the procurement documents for further information.
The competition is for the delivery of a turnkey contract with interaction for the renovation of Nesoddtangen primary school and the community centre, expansion of the school with a new building and a new multi-purpose hall. The assignment also includes the demolition of the existing gym building and development of outside areas. The project shall be carried out with the school in operation at the school and a secure school road throughout the entire construction period.
The procurement shall cover the contracting authority ́s need for a turnkey contractor, with his contractual partners for engineering design, renovation/construction and trial operation of the primary school.
Subject to political approval, re-regulation, economic coverage and other factual reasons, Nesodden municipality intends to enter into a partnering contract with the winner of the competition.
The procurement ́s value (contract cost) is estimated to be NOK 250,000,000 excluding VAT. The volume is an estimate and is not binding for the contracting authority. It is up to the parties to plan and carry out the project so that the cost frame is not exceeded.
See the procurement documents for further information.
Kontrakttype: Bygge- og anleggsarbeid
Produkter/tjenester: Bygge- og anleggsvirksomhet📦 Beskrivelse
Intern identifikator: 24017
Tilleggsprodukter/-tjenester:
The competition will be held in accordance with the Public Procurement Act from 17 June 2016 no. 73 (LOA), with the accompanying regulations of 12 August 2016 no. 974 (FOA), as well as the provisions in this tender documentation.
The competition will be held as TED - Open tender contest in accordance with the regulations Parts I and III.
All interested tenderers can submit tenders for this type of procedure. Negotiations are not allowed.
The procurement is announced in the DOFFIN and TED database.
The competition will be held in accordance with the Public Procurement Act from 17 June 2016 no. 73 (LOA), with the accompanying regulations of 12 August 2016 no. 974 (FOA), as well as the provisions in this tender documentation.
The competition will be held as TED - Open tender contest in accordance with the regulations Parts I and III.
All interested tenderers can submit tenders for this type of procedure. Negotiations are not allowed.
The procurement is announced in the DOFFIN and TED database.
Administrativ informasjon
Frist for mottak av tilbud eller forespørsler om deltakelse: 2025-03-11 11:00:58 📅
Vilkår for åpning av tilbud: 2025-03-11 11:01:00 📅
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Minste tidsramme som tilbyderen må opprettholde tilbudet i: 107 dager Anbudsvilkår
Avansert eller kvalifisert elektronisk signatur eller segl (som definert i forordning (EU) nr. 910/2014) er påkrevd
Åpningsdato: 2025-03-11 11:01:00 📅
Elektronisk katalog: Tillatt
Elektronisk fakturering: Påkrevd
Elektronisk bestilling vil bli brukt ✅
Elektronisk betaling vil bli brukt ✅
Frist for å be om tilleggsinformasjon: 2025-02-26 23:00:00 📅
Tildelingskriterier
Vekttype: Vekting (prosent, eksakt)
Juridisk, økonomisk, finansiell og teknisk informasjon Økonomisk og finansiell stilling
Liste og kort beskrivelse av utvelgelseskriterier:
Certificates for tax and VAT.: Tenderers shall have their tax and VAT payments in order (ESPD: Part II A.e).
Documentation requirement:
A certificate showing paid VAT, taxes and social security contributions is required. Certificate issued by the competent authority in the member country, confirming that the tenderer has fulfilled his VAT, tax and social security obligations in the country where the tenderer/contractor belongs (Norwegian tax and VAT certificate is common and can be ordered from altinn.no, RF-1507, previous RF-1244) in accordance with the legal provisions in the country. The certificate must not be more than six months old.
According to the regulations §17-1(4), the Contracting Authority does not have the opportunity to request the certificate if it has already been received. If you have submitted a tax certificate to the contracting authority and it is still valid at the time of the tender submission for this competition, you will not be required to present a certificate at this time. If so, state when you have previously submitted the certificate and to whom. You can, however, enclose the certificate voluntarily if you want.
In addition tenderers shall enclose a tax certificate from all sub-contractors if the contract sum for each sub-supplier exceeds NOK 500,000 excluding VAT (§7-2(3)). This shall be delivered at the latest when the contract is signed.
Certificates for tax and VAT.: Tenderers shall have their tax and VAT payments in order (ESPD: Part II A.e).
Documentation requirement:
A certificate showing paid VAT, taxes and social security contributions is required. Certificate issued by the competent authority in the member country, confirming that the tenderer has fulfilled his VAT, tax and social security obligations in the country where the tenderer/contractor belongs (Norwegian tax and VAT certificate is common and can be ordered from altinn.no, RF-1507, previous RF-1244) in accordance with the legal provisions in the country. The certificate must not be more than six months old.
According to the regulations §17-1(4), the Contracting Authority does not have the opportunity to request the certificate if it has already been received. If you have submitted a tax certificate to the contracting authority and it is still valid at the time of the tender submission for this competition, you will not be required to present a certificate at this time. If so, state when you have previously submitted the certificate and to whom. You can, however, enclose the certificate voluntarily if you want.
In addition tenderers shall enclose a tax certificate from all sub-contractors if the contract sum for each sub-supplier exceeds NOK 500,000 excluding VAT (§7-2(3)). This shall be delivered at the latest when the contract is signed.
Other economic and financial requirements: Economic and financial position.: Requirements regarding the tenderer ́s economic and financial position: The financial capacity to fulfil this contract is required (ESPD: Part IV B.58-3).
Documentation requirement:
The contracting authority will assess finances through the company and accounting information system Proff Forvalt (www.forvalt.no). The contracting authority reserves the right to obtain supplementary information about the tenderer's finances.
Any need for support from other companies to fulfil this qualification requirement.
If the tenderer is dependent on other companies to fulfil this qualification requirement, please provide an account below. The contracting authority will, in such cases, also assess the finances of the support business in the same way. The contracting authority reserves the right, in such cases, to obtain supplementary information, bank guarantees etc.
The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Other economic and financial requirements: Economic and financial position.: Requirements regarding the tenderer ́s economic and financial position: The financial capacity to fulfil this contract is required (ESPD: Part IV B.58-3).
Documentation requirement:
The contracting authority will assess finances through the company and accounting information system Proff Forvalt (www.forvalt.no). The contracting authority reserves the right to obtain supplementary information about the tenderer's finances.
Any need for support from other companies to fulfil this qualification requirement.
If the tenderer is dependent on other companies to fulfil this qualification requirement, please provide an account below. The contracting authority will, in such cases, also assess the finances of the support business in the same way. The contracting authority reserves the right, in such cases, to obtain supplementary information, bank guarantees etc.
The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Vilkår for deltakelse
Liste og kort beskrivelse av regler og kriterier:
The tenderer fulfils the stated qualification requirements:
This fulfils the objective and non-discriminatory criteria or rules that shall be used to select the number of tenderers in the following way:
If certain certificates or other forms of documentation are requested, indicate for each individual whether the tenderer is in possession of the requested documents:: If any of these certificates or other forms of documentation are available in electronic form, the certificates are to be provided for each:
This fulfils the objective and non-discriminatory criteria or rules that shall be used to select the number of tenderers in the following way:
If certain certificates or other forms of documentation are requested, indicate for each individual whether the tenderer is in possession of the requested documents:: If any of these certificates or other forms of documentation are available in electronic form, the certificates are to be provided for each:
Liste og kort beskrivelse av vilkår:
The tenderer ́s registration, authorisations, etc.: Tenderers shall be registered in a company register, professional register or a commerce register in the country where the tenderer is established. (ESPD: Part IV B.58-2).
Documentation requirement:
Norwegian companies: Company Registration Certificate
Foreign companies: Verification that the tenderer is registered in a company register, professional register or a commerce register in the country where the tenderer is established.
The tenderer ́s registration, authorisations, etc.: Tenderers shall be registered in a company register, professional register or a commerce register in the country where the tenderer is established. (ESPD: Part IV B.58-2).
Documentation requirement:
Norwegian companies: Company Registration Certificate
Foreign companies: Verification that the tenderer is registered in a company register, professional register or a commerce register in the country where the tenderer is established.
Teknisk og faglig kapasitet
Liste og kort beskrivelse av utvelgelseskriterier:
Requirements connected to the tenderer ́s technical/professional qualifications.: Tenderers shall have…
… competence and experience from assignments of a similar nature (collaboration projects), complexity, degree of difficulty and scope (ESPD: Part IV B.58-4)., i.e.
• Partnering contract/partnering
• Engineering design services for and construction of a school building or equivalent/other buildings that are relevant for this assignment.
Minimum 3 projects must have been minimum 100 mill.kr
Documentation requirement:
An overview of the most important relevant projects carried out in the last 5 years. Detailed description of 3 projects, in which the following shall be provided:
• The project name
• The contractor ́s role and assignments in the project.
• Description of the type of construction project
• Contract form (e.g. interaction)
• The contract ́s size
• The project ́s size in gross area and cost.
• Date and place of execution.
• Whether the work was carried out in accordance with the agreed time.
• Whether the work was carried out in accordance with the agreed price.
• Name of the contracting authority.
The reference person shall be given for the projects with contact information, and Nesodden municipality has the authority to contact the person in question.
Each reference project shall be for up to 1 A4 page with Calibri 11. The list of completed projects in the last five years shall be delivered on 1 A-4 page. Further information will not be considered.
Any need for support from other companies to fulfil this qualification requirement.
If the tenderer will depend on other companies to fulfil this qualification requirement, a commitment statement shall be enclosed that states that the tenderer can use the necessary resources.
The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
… a good and well-functioning quality assurance/management system (ESPD: Part IV B.58-4).
Documentation requirement:
Certificate for the company's quality system/management system issued by independent bodies that confirms the tenderer fulfils certain quality assurance standards, for example ISO certification. The contracting authority will also accept other documentation which shows that the tenderer has equivalent quality assurance measures.
Any need for support from other companies to fulfil this qualification requirement.
If the tenderer will depend on other companies to fulfil this qualification requirement, a commitment statement shall be enclosed that states that the tenderer can use the necessary resources.
The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Vilkår for deltakelse
Utestengelsesgrunn:
Akkord med kreditorer
Avtaler med andre økonomiske aktører som har til formål å vri konkurransen
Barnearbeid og andre former for menneskehandel
+ 20 til
Bedrageri
Betaling av skatter
Betaling av trygdeavgifter
Brudd på forpliktelser på arbeidsrettens område
Brudd på forpliktelser på miljørettens område
Brudd på forpliktelser på sosialrettens område
Deltakelse i en kriminell organisasjon
Direkte eller indirekte deltakelse i forberedelsen av denne anskaffelsen
Eiendeler under administrasjon av bobestyrer
Forretningsvirksomheten er suspendert
Hvitvasking eller terrorfinansiering
Insolvens
Interessekonflikt på grunn av deltakelse i anskaffelsesprosedyren
Konkurs
Korrupsjon
Situasjon tilsvarende konkurs etter nasjonal lovgivning
Skyldig i alvorlige feil i yrkesutøvelsen
Skyldig i uriktig fremstilling, tilbakeholdt informasjon, ute av stand til å fremlegge nødvendige dokumenter og innhentet konfidensiell informasjon om denne prosedyren
Terrorhandlinger eller handlinger knyttet til terrorvirksomhet
Tidlig heving, erstatning eller andre sammenlignbare sanksjoner
Beskrivelse av utelukkelsesgrunner:
Is the supplier in a situation where he has been forced debt arrangement? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the supplier in a situation where he has been forced debt arrangement? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the tenderer in a bankruptcy situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the tenderer in a bankruptcy situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies,…
… in the event a enforceable verdict has been convicted of corruption by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Corruption as defined in Article 3 of the Convention on Combating Corruption, Involving European Communities or European Union Member States (EUT C 195 of 25.6.1997, s. 1), and in Article 2, point 1, in the Council ́s framework decision 2003/568/RIA of 22 July 2003 on combating corruption in the private sector (EUT L 192 of 31.7.2003, p. 54). This rejection reason also includes corruption as defined in national law for the contracting authority or supplier.
… at the time a legally convicted verdict of participation in a criminal organisation by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Participation in a criminal organisation as defined in Article 2 of the Council ́s framework decision 2008/841/RIA of 24 October 2008 on control of organised crime (EUT L 300 of 11.11.2008, p. 42)
Has the tenderer entered into agreement(s) with other tenderers with the intention of turning the competition?
Is the tenderer aware of breaches of environmental provisions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies,…
… in the event a legal verdict has been convicted of money laundering or financing terrorism by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Money laundering or financing terrorism As defined in Article 1 of the European Parliament and Council Directive 2005/60/EF of 26 October 2005 on preventive measures against the use of the financial system for money laundering and financing terrorism (EUT L 309 of 25.11.2005, p. 15).
… at the time a legally convicted of fraud has been convicted of fraud by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Fraud included in Article 1 of the Convention on protection of the Financial Interests of the European Communities (EFT C 316 of 27.11.1995, p. 48).
… in the event a legal verdict has been convicted of child labour and other forms of human trafficking by a verdict handed down no more than five years ago, or a rejection period determined directly in the judgement that still applies? Child labour and other forms of human trafficking as defined in Article 2 of the European Parliament and council directive 2011/36/EU of 5. 1 April 2011 on the prevention and control of human trafficking and the protection of its victims and for compensation of the Council ́s framework decision 2002/629/RIA (EUT L 101 of 15.4.2011, p. 1).
Is the tenderer in an insolvency situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the tenderer in an insolvency situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Is the tenderer aware of breaches of provisions on working conditions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers made mandatory in accordance with the current national law without the possibility for exceptions.
Has the tenderer: a) given grossly incorrect information with the notification of the information required to verify that there is no basis for rejection, or of the qualification requirements being fulfilled, b) failed to provide such information, c) made reservations immediately to present the supporting documents requested by the contracting authority, or d) improperly affected the contracting authority ́s decision process to acquire confidential information that could give this an unlawful advantage in connection with competition, or negligently has given misleading information that can have a significant influence on decisions on rejection, selection or award?
Has the tenderer: a) given grossly incorrect information with the notification of the information required to verify that there is no basis for rejection, or of the qualification requirements being fulfilled, b) failed to provide such information, c) made reservations immediately to present the supporting documents requested by the contracting authority, or d) improperly affected the contracting authority ́s decision process to acquire confidential information that could give this an unlawful advantage in connection with competition, or negligently has given misleading information that can have a significant influence on decisions on rejection, selection or award?
Are tenderers aware of a conflict of interest as stated in national law, the relevant notice or procurement documents?
Has the tenderer or an entity associated with the supplier advised the contracting authority or in another way been involved in the planning of the competition?
Has the tenderer committed serious errors in professional practice? If relevant, see the definitions in national law, the relevant notice or procurement documents.
Has the tenderer committed significant breaches of contract in connection with the fulfilment of a previous public contract, a previous contract with a public contracting authority or a previous concession contract, where the breach has led to the cancellation of the contract, compensation or other similar sanctions?
Has the tenderer committed significant breaches of contract in connection with the fulfilment of a previous public contract, a previous contract with a public contracting authority or a previous concession contract, where the breach has led to the cancellation of the contract, compensation or other similar sanctions?
Is the tenderer aware of breaches of provisions on social conditions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Have tenderers failed to fulfil all their social security obligations in the country where they are established and in their member state, if this is a different country than what he is established in?
Has the tenderer not fulfilled his tax and duty obligations in the country in which he is established, and in the contracting authority's member state, if this is a different country than what he is established in?
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body, or has the competence to represent or control or make decisions in such bodies, in the event a legal verdict has been convicted of acts of terrorism or criminal acts connected to terrorist activities by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Acts of terrorism or criminal acts relating to terrorist activity as defined in Article 1 and 3 of the Council ́s framework decision 2002/475/RIA of 13 June 2002 on combating terrorism (EFT L 164, af 22.6.2002, p. 3). This rejection reason also includes incitement to, participation or attempts to commit such actions as included in Article 4 in the mentioned framework decision.
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body, or has the competence to represent or control or make decisions in such bodies, in the event a legal verdict has been convicted of acts of terrorism or criminal acts connected to terrorist activities by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Acts of terrorism or criminal acts relating to terrorist activity as defined in Article 1 and 3 of the Council ́s framework decision 2002/475/RIA of 13 June 2002 on combating terrorism (EFT L 164, af 22.6.2002, p. 3). This rejection reason also includes incitement to, participation or attempts to commit such actions as included in Article 4 in the mentioned framework decision.
Kunngjøring av konkurranse (2025-02-28) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The competition is for the delivery of a turnkey contract with interaction for the renovation of Nesoddtangen primary school and the community centre, expansion of the school with a new building and a new multi-purpose hall. The assignment also includes the demolition of the existing gym building and development of outside areas. The project shall be carried out with the school in operation at the school and a secure school road throughout the entire construction period. The procurement shall cover the contracting authority ́s need for a turnkey contractor, with his contractual partners for engineering design, renovation/construction and trial operation of the primary school. Subject to political approval, re-regulation, economic coverage and other factual reasons, Nesodden municipality intends to enter into a partnering contract with the winner of the competition. The procurement ́s value (contract cost) is estimated to be NOK 250,000,000 excluding VAT. The volume is an estimate and is not binding for the contracting authority. It is up to the parties to plan and carry out the project so that the cost frame is not exceeded. See the procurement documents for further information.
The competition is for the delivery of a turnkey contract with interaction for the renovation of Nesoddtangen primary school and the community centre, expansion of the school with a new building and a new multi-purpose hall. The assignment also includes the demolition of the existing gym building and development of outside areas. The project shall be carried out with the school in operation at the school and a secure school road throughout the entire construction period. The procurement shall cover the contracting authority ́s need for a turnkey contractor, with his contractual partners for engineering design, renovation/construction and trial operation of the primary school. Subject to political approval, re-regulation, economic coverage and other factual reasons, Nesodden municipality intends to enter into a partnering contract with the winner of the competition. The procurement ́s value (contract cost) is estimated to be NOK 250,000,000 excluding VAT. The volume is an estimate and is not binding for the contracting authority. It is up to the parties to plan and carry out the project so that the cost frame is not exceeded. See the procurement documents for further information.
Prosedyre Prosedyretype
Hovedtrekk ved prosedyren:
The competition will be held in accordance with the Public Procurement Act from 17 June 2016 no. 73 (LOA), with the accompanying regulations of 12 August 2016 no. 974 (FOA), as well as the provisions in this tender documentation. The competition will be held as TED - Open tender contest in accordance with the regulations Parts I and III. All interested tenderers can submit tenders for this type of procedure. Negotiations are not allowed. The procurement is announced in the DOFFIN and TED database.
The competition will be held in accordance with the Public Procurement Act from 17 June 2016 no. 73 (LOA), with the accompanying regulations of 12 August 2016 no. 974 (FOA), as well as the provisions in this tender documentation. The competition will be held as TED - Open tender contest in accordance with the regulations Parts I and III. All interested tenderers can submit tenders for this type of procedure. Negotiations are not allowed. The procurement is announced in the DOFFIN and TED database.
Administrativ informasjon
Frist for mottak av tilbud eller forespørsler om deltakelse: 2025-03-17 11:00:58 📅
Vilkår for åpning av tilbud: 2025-03-17 11:01:00 📅
Anbudsvilkår
Åpningsdato: 2025-03-17 11:01:00 📅
Frist for å be om tilleggsinformasjon: 2025-03-05 23:00:00 📅
Juridisk, økonomisk, finansiell og teknisk informasjon Økonomisk og finansiell stilling
Liste og kort beskrivelse av utvelgelseskriterier:
Certificates for tax and VAT.: Tenderers shall have their tax and VAT payments in order (ESPD: Part II A.e). Documentation requirement: A certificate showing paid VAT, taxes and social security contributions is required. Certificate issued by the competent authority in the member country, confirming that the tenderer has fulfilled his VAT, tax and social security obligations in the country where the tenderer/contractor belongs (Norwegian tax and VAT certificate is common and can be ordered from altinn.no, RF-1507, previous RF-1244) in accordance with the legal provisions in the country. The certificate must not be more than six months old. According to the regulations §17-1(4), the Contracting Authority does not have the opportunity to request the certificate if it has already been received. If you have submitted a tax certificate to the contracting authority and it is still valid at the time of the tender submission for this competition, you will not be required to present a certificate at this time. If so, state when you have previously submitted the certificate and to whom. You can, however, enclose the certificate voluntarily if you want. In addition tenderers shall enclose a tax certificate from all sub-contractors if the contract sum for each sub-supplier exceeds NOK 500,000 excluding VAT (§7-2(3)). This shall be delivered at the latest when the contract is signed.
Certificates for tax and VAT.: Tenderers shall have their tax and VAT payments in order (ESPD: Part II A.e). Documentation requirement: A certificate showing paid VAT, taxes and social security contributions is required. Certificate issued by the competent authority in the member country, confirming that the tenderer has fulfilled his VAT, tax and social security obligations in the country where the tenderer/contractor belongs (Norwegian tax and VAT certificate is common and can be ordered from altinn.no, RF-1507, previous RF-1244) in accordance with the legal provisions in the country. The certificate must not be more than six months old. According to the regulations §17-1(4), the Contracting Authority does not have the opportunity to request the certificate if it has already been received. If you have submitted a tax certificate to the contracting authority and it is still valid at the time of the tender submission for this competition, you will not be required to present a certificate at this time. If so, state when you have previously submitted the certificate and to whom. You can, however, enclose the certificate voluntarily if you want. In addition tenderers shall enclose a tax certificate from all sub-contractors if the contract sum for each sub-supplier exceeds NOK 500,000 excluding VAT (§7-2(3)). This shall be delivered at the latest when the contract is signed.
Other economic and financial requirements: Economic and financial position.: Requirements regarding the tenderer ́s economic and financial position: The financial capacity to fulfil this contract is required (ESPD: Part IV B.58-3). Documentation requirement: The contracting authority will assess finances through the company and accounting information system Proff Forvalt (www.forvalt.no). The contracting authority reserves the right to obtain supplementary information about the tenderer's finances. Any need for support from other companies to fulfil this qualification requirement. If the tenderer is dependent on other companies to fulfil this qualification requirement, please provide an account below. The contracting authority will, in such cases, also assess the finances of the support business in the same way. The contracting authority reserves the right, in such cases, to obtain supplementary information, bank guarantees etc. The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Other economic and financial requirements: Economic and financial position.: Requirements regarding the tenderer ́s economic and financial position: The financial capacity to fulfil this contract is required (ESPD: Part IV B.58-3). Documentation requirement: The contracting authority will assess finances through the company and accounting information system Proff Forvalt (www.forvalt.no). The contracting authority reserves the right to obtain supplementary information about the tenderer's finances. Any need for support from other companies to fulfil this qualification requirement. If the tenderer is dependent on other companies to fulfil this qualification requirement, please provide an account below. The contracting authority will, in such cases, also assess the finances of the support business in the same way. The contracting authority reserves the right, in such cases, to obtain supplementary information, bank guarantees etc. The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Vilkår for deltakelse
Liste og kort beskrivelse av regler og kriterier:
This fulfils the objective and non-discriminatory criteria or rules that shall be used to select the number of tenderers in the following way: If certain certificates or other forms of documentation are requested, indicate for each individual whether the tenderer is in possession of the requested documents:: If any of these certificates or other forms of documentation are available in electronic form, the certificates are to be provided for each:
This fulfils the objective and non-discriminatory criteria or rules that shall be used to select the number of tenderers in the following way: If certain certificates or other forms of documentation are requested, indicate for each individual whether the tenderer is in possession of the requested documents:: If any of these certificates or other forms of documentation are available in electronic form, the certificates are to be provided for each:
Liste og kort beskrivelse av vilkår:
The tenderer ́s registration, authorisations, etc.: Tenderers shall be registered in a company register, professional register or a commerce register in the country where the tenderer is established. (ESPD: Part IV B.58-2). Documentation requirement: Norwegian companies: Company Registration Certificate Foreign companies: Verification that the tenderer is registered in a company register, professional register or a commerce register in the country where the tenderer is established.
The tenderer ́s registration, authorisations, etc.: Tenderers shall be registered in a company register, professional register or a commerce register in the country where the tenderer is established. (ESPD: Part IV B.58-2). Documentation requirement: Norwegian companies: Company Registration Certificate Foreign companies: Verification that the tenderer is registered in a company register, professional register or a commerce register in the country where the tenderer is established.
Teknisk og faglig kapasitet
Liste og kort beskrivelse av utvelgelseskriterier:
Requirements connected to the tenderer ́s technical/professional qualifications.: Tenderers shall have…
… competence and experience from assignments of a similar nature (collaboration projects), complexity, degree of difficulty and scope (ESPD: Part IV B.58-4)., i.e. • Partnering contract/partnering • Engineering design services for and construction of a school building or equivalent/other buildings that are relevant for this assignment. Minimum 3 projects must have been minimum 100 mill.kr Documentation requirement: An overview of the most important relevant projects carried out in the last 5 years. Detailed description of 3 projects, in which the following shall be provided: • The project name • The contractor ́s role and assignments in the project. • Description of the type of construction project • Contract form (e.g. interaction) • The contract ́s size • The project ́s size in gross area and cost. • Date and place of execution. • Whether the work was carried out in accordance with the agreed time. • Whether the work was carried out in accordance with the agreed price. • Name of the contracting authority. The reference person shall be given for the projects with contact information, and Nesodden municipality has the authority to contact the person in question. Each reference project shall be for up to 1 A4 page with Calibri 11. The list of completed projects in the last five years shall be delivered on 1 A-4 page. Further information will not be considered. Any need for support from other companies to fulfil this qualification requirement. If the tenderer will depend on other companies to fulfil this qualification requirement, a commitment statement shall be enclosed that states that the tenderer can use the necessary resources. The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
… a good and well-functioning quality assurance/management system (ESPD: Part IV B.58-4). Documentation requirement: Certificate for the company's quality system/management system issued by independent bodies that confirms the tenderer fulfils certain quality assurance standards, for example ISO certification. The contracting authority will also accept other documentation which shows that the tenderer has equivalent quality assurance measures. Any need for support from other companies to fulfil this qualification requirement. If the tenderer will depend on other companies to fulfil this qualification requirement, a commitment statement shall be enclosed that states that the tenderer can use the necessary resources. The supporting company must also submit a separate tax certificate and ESPD form. Add any such companies that you depend on in the "sub-supplier" section of Tendsign and fill in a separate ESPD form for them.
Vilkår for deltakelse
Beskrivelse av utelukkelsesgrunner:
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, in the event a enforceable verdict has been convicted of corruption by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Corruption as defined in Article 3 of the Convention on Combating Corruption, Involving European Communities or European Union Member States (EUT C 195 of 25.6.1997, s. 1), and in Article 2, point 1, in the Council ́s framework decision 2003/568/RIA of 22 July 2003 on combating corruption in the private sector (EUT L 192 of 31.7.2003, p. 54). This rejection reason also includes corruption as defined in national law for the contracting authority or supplier.
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, in the event a enforceable verdict has been convicted of corruption by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Corruption as defined in Article 3 of the Convention on Combating Corruption, Involving European Communities or European Union Member States (EUT C 195 of 25.6.1997, s. 1), and in Article 2, point 1, in the Council ́s framework decision 2003/568/RIA of 22 July 2003 on combating corruption in the private sector (EUT L 192 of 31.7.2003, p. 54). This rejection reason also includes corruption as defined in national law for the contracting authority or supplier.
Endringer Tekst som skal korrigeres i den opprinnelige kunngjøringen
Identifikasjonsnummer for delkontrakt: LOT-0000 Informasjon om endringer
Identifikator for endret kunngjøringsversjon: bb4c34eb-8851-48fd-83f4-4f9a91199321-01
Kilde: OJS 2025/S 043-136949 (2025-02-28)