The notice applies to Egersund landstrøm AS Egersund Landstrøm is a subsidiary to Dalane Energi AS. ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’) The project includes 4 berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO and 2 berth points Dock 1DS. The objective of the dock is to establish 4 shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30.11.2020.
Frist
Fristen for mottak av tilbud var 2020-03-23.
Anskaffelsen ble publisert 2020-02-25.
Kunngjøring av konkurranse (2020-02-25) Gjenstand Anskaffelsens omfang
Tittel: Electric motors, generators and transformers
Kort beskrivelse:
The notice applies to Egersund landstrøm AS
Egersund Landstrøm is a subsidiary to Dalane Energi AS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’) The project includes 4 berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO and 2 berth points Dock 1DS.
The objective of the dock is to establish 4 shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30.11.2020.
Egersund Landstrøm is a subsidiary to Dalane Energi AS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’) The project includes 4 berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO and 2 berth points Dock 1DS.
The objective of the dock is to establish 4 shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30.11.2020.
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Egersund Landstrøm is a subsidiary to Dalane Energi AS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’) The project includes 4 berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO and 2 berth points Dock 1DS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’) The project includes 4 berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO and 2 berth points Dock 1DS.
The objective of the dock is to establish 4 shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30.11.2020.
The objective of the dock is to establish 4 shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30.11.2020.
Estimert totalverdi: 6 000 000 NOK 💰
Estimert verdi eksklusive mva: 6 000 000 NOK 💰
Beskrivelse av fornyelser: Options for further extension.
Beskrivelse av opsjoner: Further extension in accordance with the tender documentation.
Prosedyre
Rettslig grunnlag: 32014L0024
Tidspunkt for mottak av tilbud: 13:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 4 måneder
Dato for åpning av tilbud: 2020-03-23 📅
Tidspunkt for åpning av tilbud: 13:30
Tilleggsinformasjon (2020-03-17) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
The notice applies to Egersund Landstrøm AS
Egersund Landstrøm is a subsidiary to Dalane Energi AS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’). The project includes four berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO, and two berth points Dock 1DS.
The objective of the dock is to establish four shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30 November 2020.
Egersund Landstrøm is a subsidiary to Dalane Energi AS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’). The project includes four berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO, and two berth points Dock 1DS.
The objective of the dock is to establish four shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30 November 2020.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’). The project includes four berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO, and two berth points Dock 1DS.
ENOVA has granted Egersund Landstrøm AS financial support for the establishment of an shore power plant referred to as ‘Kaupanes Fase-2’ (‘Kaupanes phase 2’). The project includes four berth points in the Kaupanes area, Dock 14 and at the town side of Egersund. Dock 26NO, and two berth points Dock 1DS.
The objective of the dock is to establish four shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30 November 2020.
The objective of the dock is to establish four shore power supply points that are adapted to the different types mooring vessels. Most of the vessels are fishing vessels. However, some bulk and dry goods vessels must can also be expected. Henceforth the shore power development project shall be referred to as construction phase 2. To be commissioned by 30 November 2020.