Touch-up Painting on 58 MX3000 Underground Trains

Sporveien AS

Painted surfaces on trains are to be upgraded, limited to between the bottom boom and roof.
In addition, the trains must be marked in accordance with the new design programme.
The contracting authority needs assistance with painting and touch-up painting on MX3000 underground trains delivered by Siemens. The contracting authority will provide premises for carrying out the work. The tenderer must provide all other equipment for the work.
The procurement consists of painting and touch-up painting on 58 of the contracting authority's 115 trains. The estimated contract value of this contract is between 9 000 000 NOK-11 000 000 NOK.
Start-up will be at the turn of the month February/March 2020, at an estimated rate of one train per week. The contract will be completed when all 58 trains have been painted and delivered. The estimated execution period is 65 weeks.

Frist

Fristen for mottak av tilbud var 2020-01-06. Anskaffelsen ble publisert 2019-12-02.

Hvem? Hva? Hvor?
Anskaffelseshistorikk
Dato Dokument
2019-12-02 Kunngjøring av konkurranse
2020-07-06 Kunngjøring om tildeling av kontrakt
Kunngjøring av konkurranse (2019-12-02)
Gjenstand
Anskaffelsens omfang
Tittel: Varnishes
Referansenummer: KON-01247
Kort beskrivelse:
Painted surfaces on trains are to be upgraded, limited to between the bottom boom and roof. In addition, the trains must be marked in accordance with the new design programme. The contracting authority needs assistance with painting and touch-up painting on MX3000 underground trains delivered by Siemens. The contracting authority will provide premises for carrying out the work. The tenderer must provide all other equipment for the work. The procurement consists of painting and touch-up painting on 58 of the contracting authority's 115 trains. The estimated contract value of this contract is between 9 000 000 NOK-11 000 000 NOK. Start-up will be at the turn of the month February/March 2020, at an estimated rate of one train per week. The contract will be completed when all 58 trains have been painted and delivered. The estimated execution period is 65 weeks.
Vis mer
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Tjenester
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS)
Felles innkjøpsordliste (CPV)
Kode: Lakker 📦
Tilleggs-CPV: Maling, lakk og mastiks 📦
Utførelsessted
NUTS-region: Oslo 🏙️

Prosedyre
Prosedyretype: Konkurranse med forhandling
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet

Oppdragsgiver
Identitet
Land: Norge 🇳🇴
Type tildelende myndighet: Forsyningsenhet
Navn på tildelende myndighet: Sporveien AS
Postadresse: Økernveien 9
Postnummer: 0608
Poststed: Oslo
Kontakt
Internettadresse: http://http://www.sporveien.com 🌏
E-post: eirik.stensby.nordhaug@sporveien.com 📧
Telefon: +47 22084000 📞
URL for dokumenter: https://anbud.sporveien.com/sporveien/ 🌏

Referanse
Datoer
Sendt dato: 2019-12-02 📅
Innleveringsfrist: 2020-01-06 📅
Publiseringsdato: 2019-12-05 📅
Identifikatorer
Kunngjøringsnummer: 2019/S 235-577395
OJ-S-utgave: 235

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
Painted surfaces on trains are to be upgraded, limited to between the bottom boom and roof.
In addition, the trains must be marked in accordance with the new design programme.
The contracting authority needs assistance with painting and touch-up painting on MX3000 underground trains delivered by Siemens. The contracting authority will provide premises for carrying out the work. The tenderer must provide all other equipment for the work.
Vis mer
The procurement consists of painting and touch-up painting on 58 of the contracting authority's 115 trains. The estimated contract value of this contract is between 9 000 000 NOK-11 000 000 NOK.
Start-up will be at the turn of the month February/March 2020, at an estimated rate of one train per week. The contract will be completed when all 58 trains have been painted and delivered. The estimated execution period is 65 weeks.
Estimert totalverdi: 10 000 000 NOK 💰
Kort beskrivelse:
The contracting authority needs assistance with painting and touch-up painting on MX3000 underground trains delivered by Siemens. The contracting authority will provide premises for carrying out the work. The Tenderer must provide all other equipment for the work.
Vis mer
Varighet: 16 måneder
Utførelsessted
Hovedsted eller utførelsessted: Majorstua.

Prosedyre
Rettslig grunnlag: 32014L0025
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 3 måneder

Oppdragsgiver
Identitet
Nasjonalt registreringsnummer: 915 070 434
Kontakt
Kontaktpunkt: Eirik Nordhaug
Adresse til kjøperprofilen: https://kgv.doffin.no/ctm/Company/CompanyInformation/Index/1128 🌏
URL for dokumenter: https://anbud.sporveien.com/sporveien/ 🌏

Utfyllende informasjon
Klageinstans
Navn: Sporveien AS
Poststed: Oslo
Land: Norge 🇳🇴
Kilde: OJS 2019/S 235-577395 (2019-12-02)
Kunngjøring om tildeling av kontrakt (2020-07-06)
Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
Upgrade of laquered areas on the Oslo Metro Trains according to given design program. Total number of Trains to be lacquered is 58 of Sporveiens total of 115 Trains. Estimated contract value i between NOK 9 million-NOK 11 million. Contract start is estimated to be February/March 2020 and completed following the finished 58 Trains. Estimated execution time is set to 65 weeks.
Vis mer
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt

Prosedyre
Tilbudstype: Ikke aktuelt

Oppdragsgiver
Kontakt
Internettadresse: http://www.sporveien.com 🌏

Referanse
Datoer
Sendt dato: 2020-07-06 📅
Publiseringsdato: 2020-07-08 📅
Identifikatorer
Kunngjøringsnummer: 2020/S 130-320283
Refererer til kunngjøring: 2019/S 235-577395
OJ-S-utgave: 130

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
Upgrade of laquered areas on the Oslo Metro Trains according to given design program.
Total number of Trains to be lacquered is 58 of Sporveiens total of 115 Trains. Estimated contract value i between NOK 9 million-NOK 11 million.
Contract start is estimated to be February/March 2020 and completed following the finished 58 Trains. Estimated execution time is set to 65 weeks.

Tildeling av kontrakt
Dato for kontraktinngåelse: 2020-02-03 📅
Informasjon om tilbud
Antall mottatte tilbud: 1

Utfyllende informasjon
Klageinstans
Navn: Oslo District Court
Kilde: OJS 2020/S 130-320283 (2020-07-06)