Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water. Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian vba) via an inlet pump station located near the shoreline. The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc. The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility. Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B. The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019 Click here: https://permalink.mercell.com/102615236.aspx
Frist
Fristen for mottak av tilbud var 2019-06-17.
Anskaffelsen ble publisert 2019-05-14.
Kunngjøring av konkurranse (2019-05-14) Gjenstand Anskaffelsens omfang
Tittel: Reservoir construction works
Kort beskrivelse:
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian vba) via an inlet pump station located near the shoreline.
The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc.
The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility.
Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019
Click here: https://permalink.mercell.com/102615236.aspx
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian vba) via an inlet pump station located near the shoreline.
The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc.
The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility.
Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian vba) via an inlet pump station located near the shoreline.
The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc.
The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility.
Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019
The contract (contract E 3-3) shall primarily include the following
— inlet pipe, d= 250 mm PE, length approx. 860 m with pipe ends, etc.,
— the delivery and assembly of fibreglass armour unsaturated polyester, possible PE and a superstructure,
— excavation works, possible blasting, etc., for trenches at the land site and inlet basin,
— jack leg d= 280 mm SDR 11 with discharge in shallow water.
Utførelsessted
Hovedsted eller utførelsessted: Kvam
Prosedyre
Rettslig grunnlag: 32014L0025
Tidspunkt for mottak av tilbud: 12:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 3 måneder
Dato for åpning av tilbud: 2019-06-17 📅
Tidspunkt for åpning av tilbud: 12:00
Utfyllende informasjon Klageinstans
Navn: Nord-Fron kommune
Poststed: Vinstra
Postnummer: 2640
Land: Norge 🇳🇴
Kilde: OJS 2019/S 094-228461 (2019-05-14)
Kunngjøring om tildeling av kontrakt (2019-06-24) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian VBA) via an inlet pump station located near the shoreline.
The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc.
The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility.
Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019.
Nord-Fron municipality shall construct a new water supply facility at Kvamsfjellet, north of Rondane National Park. New water and sewage pipes, a new elevated basin and a new water treatment facility shall be constructed with the Furusjøen sea as a source of water.
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian VBA) via an inlet pump station located near the shoreline.
The works in this contract include an inlet pipe in the Furusjøen sea for Furusjøen waterworks facility, including trench works and inlet basin, etc.
The contractor must co-ordinate the progress and interface to the other contracts included in the water treatment facility.
Contract regulations in accordance with NS 8406 including amendments/additions as stated in the tender documentation chapter B.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019.
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
Prosedyre
Tilbudstype: Ikke aktuelt
Referanse Datoer
Sendt dato: 2019-06-24 📅
Publiseringsdato: 2019-06-26 📅
Identifikatorer
Kunngjøringsnummer: 2019/S 121-297582
Refererer til kunngjøring: 2019/S 094-228461
OJ-S-utgave: 121
Gjenstand Anskaffelsens omfang
Kort beskrivelse:
Raw water from the Furusjøen sea shall be collected at 14 metres depth and pumped in to the water treatment plant (Norwegian VBA) via an inlet pump station located near the shoreline.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019.
The contract is expected to be initiated by the beginning of July 2019. The contract shall be executed in such a manner that all onshore excavation works that affect the Furusjøen sea must be completed by 15.9.2019. The contract must be completed by 15.11.2019.
— excavation works, possible blasting etc., for trenches at the land site and inlet basin,