Orkdal Municipality shall establish a new water supply from Steinshaugen. 3 ground water wells have been established and shall be expanded. The following shall be constructed: a new water treatment plant, a local waste water plant, transfer system for drinking water to the new elevated basin at Digerås before connecting to the existing water supply system at Fannrem. This contract — E08 — concerns the third part of the transfer system, from the future elevated basin at Digerås to Brekka. The entire project will be carried out as joint projects with start up at different dates throughout the construction period of approx. 2 and a half years. The remaining contracts will be announced consecutively. E08 comprises excavation work for and delivery/assembly of material for approx.:
— approx. 900 m Ø400 mm water pipeline, with the accompanying manholes and other installations,
— approx. 500 m drainage and surface water pipeline in dimensions Ø200-315 mm, with the accompanying manholes and other installations,
— approx. 900 m conduits for fibre,
— crossing roads and streams.
Frist
Fristen for mottak av tilbud var 2019-04-24.
Anskaffelsen ble publisert 2019-03-21.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2019-03-21) Gjenstand Anskaffelsens omfang
Tittel: Ancillary works for pipelines and cables
Referansenummer: 536689-08
Kort beskrivelse:
“Orkdal Municipality shall establish a new water supply from Steinshaugen. 3 ground water wells have been established and shall be expanded. The following...”
Kort beskrivelse
Orkdal Municipality shall establish a new water supply from Steinshaugen. 3 ground water wells have been established and shall be expanded. The following shall be constructed: a new water treatment plant, a local waste water plant, transfer system for drinking water to the new elevated basin at Digerås before connecting to the existing water supply system at Fannrem. This contract — E08 — concerns the third part of the transfer system, from the future elevated basin at Digerås to Brekka. The entire project will be carried out as joint projects with start up at different dates throughout the construction period of approx. 2 and a half years. The remaining contracts will be announced consecutively. E08 comprises excavation work for and delivery/assembly of material for approx.:
Prosedyre
Prosedyretype: Konkurranse med forhandling
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Kunngjøring om tildeling av kontrakt (2019-08-21) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
“Orkdal Municipality shall establish a new water supply from Steinshaugen. 3 ground water wells have been established and shall be expanded. The following...”
Kort beskrivelse
Orkdal Municipality shall establish a new water supply from Steinshaugen. 3 ground water wells have been established and shall be expanded. The following shall be constructed: a new water treatment plant, a local waste water plant, transfer system for drinking water to the new elevated basin at Digerås before connecting to the existing water supply system at Fannrem. This contract -E08 — concerns the third part of the transfer system, from the future elevated basin at Digerås to Brekka. The entire project will be carried out as joint projects with start up at different dates throughout the construction period of approx. 2 and a half years. The remaining contracts will be announced consecutively. E08 comprises excavation work for and delivery/assembly of material for approx.
Vis mer
Totalverdi for anskaffelsen: 8 382 116 NOK 💰