Enova has awarded Bergen og Omland Port Authority NOK 16.1 million to develop three new on-shore electricity systems for supply boats. There are already three land electricity facilities for offshore at Skolten. The aim is between six and nine ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to two tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information about the content of the procurement, refer to the Requirement Specification and sub annex.
Frist
Fristen for mottak av tilbud var 2018-01-05.
Anskaffelsen ble publisert 2017-12-05.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2017-12-05) Gjenstand Anskaffelsens omfang
Tittel: Installation of cable infrastructure
Referansenummer: EØS 079-2017
Kort beskrivelse:
Enova has awarded Bergen og Omland Port Authority NOK 16.1 million to develop three new on-shore electricity systems for supply boats. There are already three land electricity facilities for offshore at Skolten. The aim is between six and nine ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to two tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information about the content of the procurement, refer to the Requirement Specification and sub annex.
Enova has awarded Bergen og Omland Port Authority NOK 16.1 million to develop three new on-shore electricity systems for supply boats. There are already three land electricity facilities for offshore at Skolten. The aim is between six and nine ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to two tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information about the content of the procurement, refer to the Requirement Specification and sub annex.
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Varer
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Kabelinfrastruktur📦
Tilleggs-CPV: Elektrisitet, oppvarming, solenergi og kjernefysisk energi📦 Utførelsessted
NUTS-region: Hordaland
🏙️
Prosedyre
Prosedyretype: Konkurranse med forhandling
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Gjenstand Anskaffelsens omfang
Estimert totalverdi: 4 000 000 NOK 💰
Største antall delkontrakter per tilbyder: 2
Tittel på delkontrakt: Framework Agreements for the Purchase of Cable Management Devices with Design and Functionality Suitable to the Festningskaien (the Fortress Wharf)
Delkontraktnummer: 1
Kort beskrivelse:
Enova has awarded Bergen og Omland Port Authority NOK 16.1 million to develop three new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already three land electricity facilities for offshore at Skolten. The aim is between six and nine ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to two tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.
Enova has awarded Bergen og Omland Port Authority NOK 16.1 million to develop three new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already three land electricity facilities for offshore at Skolten. The aim is between six and nine ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to two tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.
Estimert verdi eksklusive mva: 4 000 000 NOK 💰
Varighet: 24 måneder
Beskrivelse av fornyelser:
The contract will be valid for two years from the contract signing, with an option for the contracting authority to extend the contract for up to a further two years. The total maximum contract period is four years. The contracting authority can choose to take up the option for 2 years in several stages, e.g. for 1 year at a time. Any extension shall take place with a minimum of two months' written notice before the end of a contract period.
The contract will be valid for two years from the contract signing, with an option for the contracting authority to extend the contract for up to a further two years. The total maximum contract period is four years. The contracting authority can choose to take up the option for 2 years in several stages, e.g. for 1 year at a time. Any extension shall take place with a minimum of two months' written notice before the end of a contract period.
Beskrivelse av opsjoner: Extension of service agreements, see annex 1.
Tittel på delkontrakt: Framework Agreements for the Purchase of Cable Management Devices with Design and Functionality Suited to the Container Port
Delkontraktnummer: 2
Utførelsessted
Hovedsted eller utførelsessted: Bergen, Norway.
Juridisk, økonomisk, finansiell og teknisk informasjon Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten:
Tenderers shall be registered in a company register, professional register or a trade register in the country where the tenderer is established.
Documentation:
— Norwegian companies: Company Registration Certificate,
— Foreign companies: Verification that the tenderer is registered in a company register, trade register or a commerce register in the country where the tenderer is established.
Declared. Documented upon request.
Økonomisk og finansiell stilling:
Tenderers must have sufficient economic and financial capacity to fulfil the contract. Creditworthiness with no requirement for guarantees will be sufficient to meet the requirement.
Documentation requirement:
— A credit rating based on the most recent financial figures. The rating shall be carried out by a credit rating company with licence to conduct this service.
Declared. Documented upon request.
Teknisk og faglig kapasitet:
The tenderer shall have good experience with the implementation of equivalent goods deliveries of equivalent complexity.
Documentation:
Description of up to three of the tenderer’s most relevant assignments during the last five years with information about:
1) Name of contracting authority;
2) The project name;
3) The project's nature, size, cost and complexity;
4) Date;
5) The tenderer's delivery in the project.
The contractor may do this by including documentation on the skill or experience of the personnel that can be used for this project, including skills or experience that has been acquired while the personnel was in the service of another employer.
Declared. Documented upon request.
A description of the tenderer's quality assurance methods. If the tenderer is certified in accordance with ISO 9001 or equivalent standards, it is sufficient to present a copy of a valid certificate.
Prosedyre
Antall deltakere som skal vurderes: 2
Tidspunkt for mottak av tilbud: 14:00
Språk som tilbud eller forespørsler om deltakelse kan sendes inn på: norsk 🗣️
Tilbudets gyldighetsperiode: 2018-04-30 📅
Kunngjøring om tildeling av kontrakt (2018-05-15) Gjenstand Anskaffelsens omfang
Kort beskrivelse:
Enova has awarded Bergen og Omland Port Authority 16 100 000 NOK to develop 3 new on-shore electricity systems for supply boats. There are already three land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into 2 framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information about the content of the procurement, refer to the Requirement Specification and sub annex.
Enova has awarded Bergen og Omland Port Authority 16 100 000 NOK to develop 3 new on-shore electricity systems for supply boats. There are already three land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into 2 framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority's budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information about the content of the procurement, refer to the Requirement Specification and sub annex.
Totalverdi for anskaffelsen: 10 000 000 NOK 💰
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt
Prosedyre
Tilbudstype: Ikke aktuelt
Referanse Datoer
Sendt dato: 2018-05-15 📅
Publiseringsdato: 2018-05-16 📅
Identifikatorer
Kunngjøringsnummer: 2018/S 092-210095
Refererer til kunngjøring: 2017/S 234-487295
OJ-S-utgave: 92
Gjenstand Anskaffelsens omfang
Tittel på delkontrakt: Framework agreements for the purchase of cable management devices with design and functionality suitable to the Festningskaien [the Fortress wharf].
Kort beskrivelse:
Enova has awarded Bergen og Omland Port Authority 16 100 000 NOK to develop 3 new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already 3 land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority´s budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.
Enova has awarded Bergen og Omland Port Authority 16 100 000 NOK to develop 3 new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already 3 land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into two framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority´s budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.
Tittel på delkontrakt: Framework agreements for the purchase of cable management devices with design and functionality suited to the container port.
Kort beskrivelse:
Enova has awarded Bergen og Omland Port Authority 16 100 000 to develop three new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already 3 land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into 2 framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority´s budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.
Enova has awarded Bergen og Omland Port Authority 16 100 000 to develop three new on-shore electricity systems for supply boats. The Enova resources will first enable the development of new land electricity facilities at Dokken, Nykirkekaien and Festningskaien. There are already 3 land electricity facilities for offshore at Skolten. The aim is between 6 and 9 ready developed facilities in 2018. BOH aims to enter into 2 framework agreements for the delivery and assembly of equipment for complete on-shore electricity facilities. Delivery will first be to the stated points at Dokken, Nykirkekaien and Festningskaien. Future land electricity points will depend on the contracting authority´s budget situation and future grants from Enova. One framework agreement shall be signed per contract area, with up to 2 tenderers. See point 1.e. BOH has announced separate competitions on framework agreements for the purchase of on-shore facilities. This procurement concerns framework agreements for the purchase of cable management devices out toward ships. Tenderers shall also be responsible for installation of the devices. For further information on the contents of the procurement, see Part III Annex 1 Requirement Specifications and enclosures.