Antall eller omfang
Main works with estimated quantities that are in the contract.— rigging works;— surveying;— technical checks and documentation;— blasting cutting Seljestad: 5 000 pfm3;— blasting rock matter, tunnel: 140 000 pfm3;— blasted rock matter to depot: 140 000 pfm3;— reinforcement layer 1 (0-32/10-100): 8 500 pfm3;— asphalt base course: 16 000 m2;— asphalt wearing course/binding layer: 32 000 m²;— portal Seljestad: 32 m;— portal Sama: 10 m;— temporary interim road, Seljestad;— setting up supporting walls;— kerbstone;— railings;— improvement works, electro;— Water and sewage works (pipelines, manholes, drains, etc.);— landscape works;— assembling signage;— road marking.The list is not complete, the amounts are in chapter D1 — description (ISY-GPROG).The project will be carried out on the basis of drawings. Drawings are in chapter D2.