E6 Storler — Sentervegen — Contract 2: Alterations to the Dovre railway

Statens vegvesen Region midt (The Norwegian Public Roads Administration, Region mid-Norway)

The works in contract 2 comprise laying of the Dovre track in a new route by Klett railway bridge, construction of new pedestrian and cycle pathway including new underpass under the Dovre railway with associated berm at Lersbakken.
In the lead up to this contract, contract 1 — Alteration of the Dovre railway, Preliminary works will be carried out. The construction site and construction roads established in contract 1 will be overtaken by contract 2.
The construction site and interim road for E6 under the new Klett railway bridge contract 2 shall be overtaken and utilised by the Contractor responsible for the construction of contract 3 E6 Jaktøyen — Sentervegen. The construction site's location is along the Dovre railway and close by and over E6 in Storlersbakken.
There will be traffic on the Dovre railway and along the E6 during the entire construction period, with the exception of two train free weekends for the Dovre railway, which are planned for the end of May 2016 and middle of September 2016. During train free weekends, all train traffic will be stopped and the overhead contact system will be disconnected. In train free weekends, the trains will be stopped for a minimum of 40 hours.
For the E6 it will be necessary to have traffic control and a driving lane closed in periods (at night) in connection with works by and over E6.
Alterations to the Dovre railway
In connection with the establishment of a new four lane E6 between Jaktøyen — Sentervegen, a new bridge shall be constructed for the Dovre railway with associated modification of the railway track in a stretch of approximately 700 m. A new track will be built on this stretch with new CL installation, drainage system and signal cables shall be lain in a new cable channel. To facilitate alterations during a train free weekend, some temporary KL posts must be set up along parts of the railway. Restructuring of train traffic over the new track shall occur during one of the train free weekends in September 2016.
Safety screen:
The Norwegian National Rail Administration has requirements for works on and near railway tracks in operation in regard to safety of materials, workers and third parties. In order to ease the degree of freedom for the work, as regards stopping work for passing trains and the use of security guards at works near railway tracks and electrified lines (CL-installations), an eight metre high safety screen shall be erected along the existing Dovre railway. The safety screen will be set up in ‘white periods’ between trains on the Dovre railway. In this contract, a total of approx. 445 m of safety screen shall be built beyond the site. Safety screen along the stretch shall be demolished for approx. 670 metres in length.
New Klett railway bridge
Railway bridge will be 85 m long and shall span over a new four lane E6. The bridge will have four spans and be executed as a span reinforced concrete bridge. The railway bridge's pillar axes shall be pile founded to rock with drilled and cast steel pipe piles in each axis. The abutments shall be directly founded. Pile founding shall be executed in contract 1. After restructuring of the train traffic over to a new route over the new Klett railway bridge, matter under the new bridge and existing railway filling shall be excavated.
Interim road E6
In connection with the excavation and removal of the existing railway bridge, traffic shall temporarily be diverted in a southbound lane of the new E6. Interim road shall be established with two lanes, total with 9.7 m, fixed cover and railing.
Demolition of the existing Klett railway bridge
The existing Klett railway bridge shall be demolished. Walls and ceiling of the existing construction will be removed but the foundations shall remain.
Pedestrian and cycle path, Lersbakken
A new pedestrian and cycle path shall be constructed from Heggstadmoen waste plant to Heimdalsvegen. The pedestrian and cycle path shall be constructed with a width of 5 m, gravel covered and with a closed drainage system. The pedestrian and cycle path runs partially in an area in with quick clay. A new high filling will be established for the pedestrian cycle path, which will result in increased load on the site. To reduce the load, parts of the road filling will be performed with lightweight fill matter. It will therefore be extremely important that instructions and descriptions from geotechnical reports and the Contractor's geotechnical engineering is followed in connection with the construction of the pedestrian cycle path.
Underpass:
A new underpass shall be built for the pedestrian and cycle path under the Dovre railway. The underpass will consist of prefabricated concrete elements. The underpass with wing walls, edge beams and railings will be 7 m long and have openings of w x h + 5.0 m x 4.2 m. Detailed engineering of prefabricated concrete elements is included in the delivery. The production basis must be approved by The Norwegian Public Roads Administration's Head Office before production is started. All works with a complete underpass including i.a. excavation and removal of excavated matter, establishment of drainage system, assembly of complete underpass with backfilling and re-establishment of the railway track shall be carried out during one of the train free weekends in May 2016.
Backfilling
Lersbakken pedestrian and cycle path shall be constructed in a sensitive area in regard to the stability and quick clay zones. The pedestrian and cycle path shall lie to the west of the Dovre railway, on an approx. 10-16 m high filling. To counteract the increased load from the pedestrian and cycle path in the area, a large backfilling in the lower part of the filling must be carried out in advance. The backfilling shall be built up with firm clay, dry crust clay or suitable friction matter from the excess matter in the site. The filling shall have drainage in the bottom. An open stream course shall also be established in the surface of the back filling which is rock pitched.
Noise barrier:
At Lersbakken farm, approx. 500 m north of the E6, a 2 m high noise barrier will be built toward the Dovre railway. The existing road and level crossing at Lersbakken farm will be removed.

Frist

Fristen for mottak av tilbud var 2015-08-17. Anskaffelsen ble publisert 2015-06-18.

Leverandører

Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:

Hvem? Hva? Hvor?
Anskaffelseshistorikk
Dato Dokument
2015-06-18 Kunngjøring av konkurranse
2015-07-23 Tilleggsinformasjon
2015-11-04 Kunngjøring om tildeling av kontrakt
Kunngjøring av konkurranse (2015-06-18)
Gjenstand
Anskaffelsens omfang
Tittel: Construction work
Antall eller omfang:
Alterations to the Dovre railway 700 m.New Klett railway bridge. Length 85 m. 700 m³ concrete.Excavation and matter removal 65 000 m³.Interim road E6 250 m.Pedestrian and cycle path, Lersbakken 750 m.Back filling of pedestrian and cycle path, Lersbakken 30 000 m³ uncompacted material.Prefabricated underpass for pedestrian and cycle path, Lersbakken 330 tonne.Drainage layer material 3,000 m³.Erosion protection 3 000 m².Drainage pipe 500 m.Safety screen 445 m.Noise barrier 90 m.70 000 00090 000 000
Vis mer
Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Bygge- og anleggsarbeid
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsvirksomhet 📦

Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Laveste pris

Oppdragsgiver
Identitet
Land: Norge 🇳🇴
Type tildelende myndighet: Nasjonalt eller føderalt byrå/kontor
Navn på tildelende myndighet: Statens vegvesen Region midt (the Norwegian Public Roads Administration, Region Mid-Norway)
Postadresse: Fylkeshuset
Postnummer: 6404
Poststed: Molde
Kontakt
E-post: odd-jostein.haugen@vegvesen.no 📧
Telefon: +47 91744075 📞

Referanse
Datoer
Sendt dato: 2015-06-18 📅
Innleveringsfrist: 2015-08-17 📅
Publiseringsdato: 2015-06-20 📅
Identifikatorer
Kunngjøringsnummer: 2015/S 118-216172
OJ-S-utgave: 118
Tilleggsinformasjon
Tender conference will take place at the project office to Miljøpakken in Østre Rosten 20, 7075 Tiller, 29.6.2015, at 10:00.

Gjenstand
Anskaffelsens omfang
Kort beskrivelse:
The works in contract 2 comprise laying of the Dovre track in a new route by Klett railway bridge, construction of new pedestrian and cycle pathway including new underpass under the Dovre railway with associated berm at Lersbakken.
In the lead up to this contract, contract 1 — Alteration of the Dovre railway, Preliminary works will be carried out. The construction site and construction roads established in contract 1 will be overtaken by contract 2.
The construction site and interim road for E6 under the new Klett railway bridge contract 2 shall be overtaken and utilised by the Contractor responsible for the construction of contract 3 E6 Jaktøyen — Sentervegen. The construction site's location is along the Dovre railway and close by and over E6 in Storlersbakken.
Vis mer
There will be traffic on the Dovre railway and along the E6 during the entire construction period, with the exception of two train free weekends for the Dovre railway, which are planned for the end of May 2016 and middle of September 2016. During train free weekends, all train traffic will be stopped and the overhead contact system will be disconnected. In train free weekends, the trains will be stopped for a minimum of 40 hours.
Vis mer
For the E6 it will be necessary to have traffic control and a driving lane closed in periods (at night) in connection with works by and over E6.
Alterations to the Dovre railway
In connection with the establishment of a new four lane E6 between Jaktøyen — Sentervegen, a new bridge shall be constructed for the Dovre railway with associated modification of the railway track in a stretch of approximately 700 m. A new track will be built on this stretch with new CL installation, drainage system and signal cables shall be lain in a new cable channel. To facilitate alterations during a train free weekend, some temporary KL posts must be set up along parts of the railway. Restructuring of train traffic over the new track shall occur during one of the train free weekends in September 2016.
Vis mer
Safety screen:
The Norwegian National Rail Administration has requirements for works on and near railway tracks in operation in regard to safety of materials, workers and third parties. In order to ease the degree of freedom for the work, as regards stopping work for passing trains and the use of security guards at works near railway tracks and electrified lines (CL-installations), an eight metre high safety screen shall be erected along the existing Dovre railway. The safety screen will be set up in ‘white periods’ between trains on the Dovre railway. In this contract, a total of approx. 445 m of safety screen shall be built beyond the site. Safety screen along the stretch shall be demolished for approx. 670 metres in length.
Vis mer
New Klett railway bridge
Railway bridge will be 85 m long and shall span over a new four lane E6. The bridge will have four spans and be executed as a span reinforced concrete bridge. The railway bridge's pillar axes shall be pile founded to rock with drilled and cast steel pipe piles in each axis. The abutments shall be directly founded. Pile founding shall be executed in contract 1. After restructuring of the train traffic over to a new route over the new Klett railway bridge, matter under the new bridge and existing railway filling shall be excavated.
Vis mer
Interim road E6
In connection with the excavation and removal of the existing railway bridge, traffic shall temporarily be diverted in a southbound lane of the new E6. Interim road shall be established with two lanes, total with 9.7 m, fixed cover and railing.
Demolition of the existing Klett railway bridge
The existing Klett railway bridge shall be demolished. Walls and ceiling of the existing construction will be removed but the foundations shall remain.
Pedestrian and cycle path, Lersbakken
A new pedestrian and cycle path shall be constructed from Heggstadmoen waste plant to Heimdalsvegen. The pedestrian and cycle path shall be constructed with a width of 5 m, gravel covered and with a closed drainage system. The pedestrian and cycle path runs partially in an area in with quick clay. A new high filling will be established for the pedestrian cycle path, which will result in increased load on the site. To reduce the load, parts of the road filling will be performed with lightweight fill matter. It will therefore be extremely important that instructions and descriptions from geotechnical reports and the Contractor's geotechnical engineering is followed in connection with the construction of the pedestrian cycle path.
Vis mer
Underpass:
A new underpass shall be built for the pedestrian and cycle path under the Dovre railway. The underpass will consist of prefabricated concrete elements. The underpass with wing walls, edge beams and railings will be 7 m long and have openings of w x h + 5.0 m x 4.2 m. Detailed engineering of prefabricated concrete elements is included in the delivery. The production basis must be approved by The Norwegian Public Roads Administration's Head Office before production is started. All works with a complete underpass including i.a. excavation and removal of excavated matter, establishment of drainage system, assembly of complete underpass with backfilling and re-establishment of the railway track shall be carried out during one of the train free weekends in May 2016.
Vis mer
Backfilling
Lersbakken pedestrian and cycle path shall be constructed in a sensitive area in regard to the stability and quick clay zones. The pedestrian and cycle path shall lie to the west of the Dovre railway, on an approx. 10-16 m high filling. To counteract the increased load from the pedestrian and cycle path in the area, a large backfilling in the lower part of the filling must be carried out in advance. The backfilling shall be built up with firm clay, dry crust clay or suitable friction matter from the excess matter in the site. The filling shall have drainage in the bottom. An open stream course shall also be established in the surface of the back filling which is rock pitched.
Vis mer
Noise barrier:
At Lersbakken farm, approx. 500 m north of the E6, a 2 m high noise barrier will be built toward the Dovre railway. The existing road and level crossing at Lersbakken farm will be removed.
Antall eller omfang:
Alterations to the Dovre railway 700 m.
New Klett railway bridge. Length 85 m. 700 m³ concrete.
Excavation and matter removal 65 000 m³.
Interim road E6 250 m.
Pedestrian and cycle path, Lersbakken 750 m.
Back filling of pedestrian and cycle path, Lersbakken 30 000 m³ uncompacted material.
Prefabricated underpass for pedestrian and cycle path, Lersbakken 330 tonne.
Drainage layer material 3,000 m³.
Erosion protection 3 000 m².
Drainage pipe 500 m.
Safety screen 445 m.
Noise barrier 90 m.
Estimert verdi eksklusive mva: 70 000 000 💰
90 000 000 💰
Referansenummer: 2015022099
Utførelsessted
Hovedsted eller utførelsessted: Trondheim, Norway.

Juridisk, økonomisk, finansiell og teknisk informasjon
Vilkår for deltakelse
Egnethet til å utøve yrkesvirksomheten:
(1) Requirement to submit tax certificate for VAT (National requirement).
(2) Requirement to submit a tax certificate for tax (National requirement).
(3) Requirement to submit a self-declaration in accordance with the regulations' annex 2 on HSE (National requirement)
(4) If the tenderer is a working partnership, enclosed with the tender must be a declaration on joint and several liability to the Contractor and third parties.
Økonomisk og finansiell stilling:
(1) Statement of the company's turnover for the last few years, with relevance to this contract.
(2) Tenderers shall disclose equity and total assets from the last reported accounts. If there are any significant changes to the tenderer's equity and solvency in relation to the last audited accounts, documentation about this must be attached.
Minste nivå(er) av standarder:
Tenderer must have positive equity. If the tenderer is a working partnership (supplier group), the requirements apply for each of the participants.
Teknisk og faglig kapasitet:
(1) Staffing for this assignment (organisation plan) with names and CVs of key personnel who shall carry out the assignment (applies to services, and building and construction contracts).
(2) Experiences from equivalent works. Reference projects.
(3) Contractor's experiences. Reference projects.
(4) Other (please state documentation requirement below):
The accident frequency (H1-value) for the last 3 years should be lower than 5.
Minste nivå(er) av standarder:
Requirements regarding competence of the key personnel:
Key personnel meaning site managers/operation managers, the contract manager and the HSE manager. The key personnel for this contract must have competence and experience from similar works in construction and railway engineering work in and on railways. Contractors shall document competence and experience by CVs and references for the key personnel.
Vis mer
A statement of how the tenderer will organise the execution of the contract. The important factors here include that the organisation is sufficiently staffed and that the tenderer has the capacity and ability to deal with unforeseen circumstances during the contract.
Vis mer
Kontraktutførelse
Innskudd og garantier som kreves: See the tender documentation.
Hovedfinansieringsvilkår og betalingsordninger og/eller henvisning til relevante bestemmelser som regulerer dem: See the tender documentation.
Juridisk form som skal antas av gruppen av økonomiske operatører som kontrakten skal tildeles til: See the tender documentation.

Prosedyre
Tilbudets gyldighetsperiode: 2015-10-09 📅
Dato for åpning av tilbud: 2015-08-17 📅
Åpningssted: Statens hus, Trondheim, Norway.
Sted: Statens hus, Trondheim, Norway.
Informasjon om autoriserte personer og åpningsprosedyre:
The tenders will be opened at Statens hus, Prinsens gate 1, Trondheim. Report to the reception at The Norwegian Public Roads Administration (entry from the junction between Prinsens gate and Erling Skakkes gate).
Språk
Andre språk: Norwegian.

Oppdragsgiver
Identitet
Nasjonalt registreringsnummer: 971032081
Kontakt
Kontaktpunkt: Odd Jostein Haugen
Adresse til kjøperprofilen: https://kgv.doffin.no/ctm/Supplier/CompanyInformation/Index/1111 🌏
Postadresse: Prinsens gate 1
Poststed: Trondheim
Postnummer: 7013
Kontaktpunkt: Reception at Statens hus (entry from the junction between Erling Skakkes gate and Prinsens gate)
URL for dokumenter: https://kgv.doffin.no/ctm/Supplier/Documents/Folder/133191 🌏

Referanse
Identifikatorer
Referansenummer tildelt av oppdragsgiver: 2015022099
Kilde: OJS 2015/S 118-216172 (2015-06-18)
Tilleggsinformasjon (2015-07-23)
Gjenstand
Metadata for kunngjøring
Dokumenttype: Tilleggsinformasjon

Referanse
Datoer
Sendt dato: 2015-07-23 📅
Innleveringsfrist: 2015-08-31 📅
Publiseringsdato: 2015-07-28 📅
Identifikatorer
Kunngjøringsnummer: 2015/S 143-265020
Refererer til kunngjøring: 2015/S 118-216172
OJ-S-utgave: 143
Kilde: OJS 2015/S 143-265020 (2015-07-23)
Kunngjøring om tildeling av kontrakt (2015-11-04)
Gjenstand
Anskaffelsens omfang
Totalverdi for anskaffelsen: 69 014 244,10 💰
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt

Prosedyre
Tilbudstype: Ikke aktuelt

Oppdragsgiver
Identitet
Navn på tildelende myndighet: The Norwegian Public Roads Administration, Region Mid-Norway

Referanse
Datoer
Sendt dato: 2015-11-04 📅
Publiseringsdato: 2015-11-07 📅
Identifikatorer
Kunngjøringsnummer: 2015/S 216-395085
OJ-S-utgave: 216

Gjenstand
Utførelsessted
Hovedsted eller utførelsessted: Trondheim.

Tildeling av kontrakt
Dato for kontraktinngåelse: 2015-09-15 📅
Navn: Søbstad AS
Postadresse: Sandmoveien 22
Poststed: Heimdal
Postnummer: 7072
Land: Norge 🇳🇴
Informasjon om tilbud
Antall mottatte tilbud: 5