Region Nordhordland Helsehus in Knarvik.
Nordhordland Utviklingsselskap IKS would like to join up with competence in project management for the entire process from start to completed building. The project management shall manage the project and all the accompanying processes as regards time, finances, quality, and the procurement of all the necessary services for completing the project.
The project will be carried out as a turnkey contract.
The current project status is:
— a site for the development has been chosen;
— the review project with an impact assessment, interested parties analysis and an assessment of various solutions and models for joint location have been carried out;
— tentative tenants are identified and a dialogue has been established;
— a tentative area need has been obtained;
— a sketch for the project organisation has been prepared.
The total length of the project is estimated to 4 years, with estimated completion in 2018.
Frist
Fristen for mottak av tilbud var 2014-10-24.
Anskaffelsen ble publisert 2014-09-13.
Leverandører
Følgende leverandører er nevnt i tildelingsbeslutninger eller andre anskaffelsesdokumenter:
Kunngjøring av konkurranse (2014-09-13) Gjenstand Anskaffelsens omfang
Tittel: Construction-related services
Antall eller omfang:
“Nordhordland Utviklingsselskap IKS would like to engage project management with a project manager who shall see to the implementation of the project up...”
Antall eller omfang
Nordhordland Utviklingsselskap IKS would like to engage project management with a project manager who shall see to the implementation of the project up until the turnkey building is ready for use.— The project management is expected to last for 4 years.— The project management shall, on behalf of the builders and within the fixed authorisations, ensure that the project is carried out at the right time within the agreed financial limits and with the correct quality.— The project management has a general responsibility for ensuring compliance with the public procurement regulations throughout the entire process.— The project management has a general responsibility for ensuring that the regulation process is in accordance with progress and finances.— The project management has a general responsibility for contracting an engineering design group, engineering design manager, construction management organisation and contractors.— The project management shall prepare a complete main progress plan for the entire process.— The project management shall keep project accounts continuously for all the contracts that have been signed in total for the builder. An account shall be given of the contract sum, additional and change work, wages and price rises as well as the expected unexplained costs in the coming period.— The project management shall ensure that an uncertainty analysis is carried out based on the completed preliminary project, drawings, descriptions and calculations.— The project management shall report to the management group monthly as regards progress, finances and quality.See the tender documents and annexes for further information on the contract's extent and content.
Vis mer Metadata for kunngjøring
Originalspråk: engelsk 🗣️
Dokumenttype: Kunngjøring av konkurranse
Kontraktens art: Tjenester
Forskrift: Det europeiske økonomiske samarbeidsområdet (EØS), med deltakelse av GPA-land
Felles innkjøpsordliste (CPV)
Kode: Bygge- og anleggsrelaterte tjenesteytelser📦
Prosedyre
Prosedyretype: Åpen anbudskonkurranse
Tilbudstype: Innlevering for alle delkontrakter
Tildelingskriterier
Det mest økonomisk fordelaktige tilbudet
Oppdragsgiver Identitet
Land: Norge 🇳🇴
Type tildelende myndighet: Regional eller lokal myndighet
Navn på tildelende myndighet: Nordhordland Utviklingsselskap IKS
Postadresse: Postboks 13
Postnummer: 5902
Poststed: Isdalstø
Kontakt
E-post: post@nordhordland.net📧
Telefon: +47 90753459📞
Kunngjøring om tildeling av kontrakt (2014-12-03) Gjenstand Anskaffelsens omfang
Totalverdi for anskaffelsen: 1 755 000 💰
Metadata for kunngjøring
Dokumenttype: Kunngjøring om tildeling av kontrakt